COMPANY RECORD · SEATTLE, WA

Siemens Building Technology — permit history in Seattle, WA

Siemens Building Technology appears on 73 Seattle permit records from 2020 through 2026, most often electrical (94.5% of the record).

Permit categories

CategoryPermitsShare
Electrical6994.5%
Fire protection45.5%

2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.

Activity by year

YearPermits issued
20205
202111
202215
202321
202413
20255
20263

Busiest year on record: 2023, with 21 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
7500 EAST MARGINAL WAY S2026-07-20
2208 4TH AVE2026-03-25
401 N 130TH ST2025-10-31
1700 7TH AVE2025-06-04
6846 OSWEGO PL NE2025-04-02
1483 ALASKAN WAY2025-03-20
8704 GREENWOOD AVE N2025-03-06
4800 SAND POINT WAY NE2024-10-09
912 DEXTER AVE N2024-09-06
8201 10TH AVE S2024-09-06
900 UNIVERSITY ST2024-06-24
1010 8TH AVE S2024-05-02
811 MAYNARD AVE S2024-04-10
1200 STEWART ST2024-01-30

36 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $544,657, median $6,100. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

73 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
7150892-EL2026-07-20Electrical7500 EAST MARGINAL WAY SInstall new FACP, annunciator, notification/initiating devices$26,000
7140958-EL2026-05-05Electrical7500 EAST MARGINAL WAY S*This project was permitted and inspected in King County under permit #FIRP24-0288. After final, zoning maps confirmed that this falls withing Seattle Jurisdiction. No additional s$10,000
7135264-EL2026-03-25Electrical2208 4TH AVERelocating one notification Device, Adding one new notification device and monitoring module for hood system. This is a joint venture with Siemens and KBE Electric
7087231-EL2025-10-31Electrical401 N 130TH STSiemens will terminate all existing devices, including old FACP. Siemens will install all new devices and run new wire to each device. Siemens will provide the initial walk-through$90,000
7089528-EL2025-06-04Electrical1700 7TH AVEInstalling access control devices and trimming the panel$17,000
7060477-EL2025-04-02Electrical6846 OSWEGO PL NESiemens is proposing a code compliant fire system per the spots and dots drawings provided. Fire Alarm which will include Control Panel, Annunciator, Horn Strobes, Smoke Detectors$80,748
7076573-EL2025-03-20Electrical1483 ALASKAN WAYRelocating two notification devices along with a pretest and a final.$5,200
7059978-EL2025-03-06Electrical8704 GREENWOOD AVE NThis is a parts of smarts project. Siemens will be programming and testing devices$15,463
7042224-EL2024-10-09Electrical4800 SAND POINT WAY NEAdding 10 new sampling points to existing VESDA system in PBMU Shell buildout area. This is a joint Venture with VECA and Siemens.$10,000
7037092-EL2024-10-09Electrical4800 SAND POINT WAY NESmall buildout of existing shell space in PBMU area at SCH. This is a joint venture with VECA and SIEMENS INDUSTRY$5,000
7020585-EL2024-09-06Electrical912 DEXTER AVE NSiemens will be providing a like for like panel upgrade for the site. This will include all initiating devices (smoke detectors, pull stations, relays and duct detectors). Siemens $137,625
7040369-EL2024-09-06Electrical8201 10TH AVE SInstallation of a new Fire Alarm Control Panel (FACP). Removal of the existing Fire Alarm Control Panel and Field Devices Programing detectors and Modules Replacement of Exis$64,229
7031734-EL2024-06-25Electrical4800 SAND POINT WAY NERevision to existing approved permit 7008330-EL. Remove/replacing existing notification appliances in Mountain Level 6 Area to address strobe syncing issue. This is a joint ventu$10,000
7028400-EL2024-06-24Electrical900 UNIVERSITY STThis is a revision to 7010191-EL. 3rd Floor TI space included. Addition of smoke detectors and relays for existing door holders.$34,000
7020586-EL2024-05-02Electrical1010 8TH AVE SSiemens will be taking over the existing Simplex panel that is on site. Siemens will be replacing all initiating devices (smokes, pulls and heats).$10,866
7019142-EL2024-04-10Electrical811 MAYNARD AVE SRelocated 1 pull station on site. This is a joint venture with Siemens and Cochran Inc. Unable to add Cochran on Permit due to 100+ entries into the SDCI portal.$1,000
7014763-EL2024-03-21Electrical4800 SAND POINT WAY NERevision to 6939606-EL Approved FA Drawings. Removed floor 4 from scope of work and drawings.$0
7008330-EL2024-02-19Electrical4800 SAND POINT WAY NEAdding and relocating duct detectors, initiating devices and notification devices to the Mountain Level 6 Area. This is a joint venture with Astor Electric and Siemens.$20,000
6999433-EL2024-01-30Electrical1200 STEWART STAdding VESDA Units to AHU supply/return for smoke detection and shutdown. Music Venue with production haze effects and tenant wants to try and avoid any false alarms. [12-31-24 DR$100,000
7006159-EL2024-01-24Electrical201 WESTLAKE AVE NSwapping 6 smoke detectors for heat detectors in linen rooms to prevent false alarms on site.$5,000
7004331-EL2024-01-11Electrical900 UNIVERSITY STWe are taking two apartments and turning them into one apartment. Unit: 16F and 16G - Combined into 16FG. Currently, 2 - 1bd/1ba apartment; eventually, 1 - 2bd/2ba apartment. Curre$5,000
7000743-EL2023-12-15Electrical60 YESLER WAYThis a correction to permit 6935040-EL. The wrong fire alarm plan was submitted and approved for the wrong address. We can either approve this one as new with correct address and$20,000
6998740-EL2023-12-01Electrical900 UNIVERSITY STWe are taking two apartments and turning them into one apartment. Unit: 7F and 7G - Combined into 7FG. Currently 2 - 1bd/1ba apartment; eventually 1 - 2bd/2ba apt Current Devices$10,000
6996232-EL2023-11-14Electrical725 9TH AVEAdding fire alarm relay to interface with security access control$2,000
6996044-EL2023-11-13Electrical900 UNIVERSITY STApartment 17O at Horizon House with movement of a few devices using the same device in different locations.$5,000
6990877-EL2023-10-12Electrical900 UNIVERSITY STTHIS PROJECT IS A FIRE ALARM SYSTEM TI Removing four (4) NAC Devices to replace the same devices once the TI is complete.$5,000
6987944-EL2023-10-11Electrical3201 S NORFOLK STAddition to the existing core fire alarm system with two initiating devices and 67 NAC devices.$27,000
6977796-EL2023-07-27Electrical2203 AIRPORT WAY SUpgrading from POTS lines to Tel-Guard Cell communicator$2,400
6975759-EL2023-07-17Electrical122 16TH AVE EUpgrade to main fire alarm panel only. Will be installing new updated main fire alarm panel parts. No field devices will be changed.$5,000
6966103-EL2023-06-23Electrical725 9TH AVEAdding elevator control devices to newly added elevator. Adding control devices and a few notification appliances.$5,000
6969935-EL2023-06-13Electrical122 16TH AVE EUpgrade to main fire alarm panel only. Will be installing new updated main fire alarm panel parts. No field devices will be changed.$5,000
6957487-EL2023-04-19Electrical900 UNIVERSITY STWe are moving devices around to accommodate a renovation from a medical clinic to an HR office within the Horizon House complex. There are ten devices in this TI.$5,000
6935645-EL2023-04-04Electrical1400 6TH AVEThis is a "like-in-kind" replacement of the SLC devices only. Four (4) Fire Alarm Control Panels and NAC Power Supply Panels will be used as a Like-in-kind replacement. Not a total$544,657
6955136-EL2023-03-24Electrical900 UNIVERSITY STJoint Venture with Horizon House. Moving a few devices for a renovation.$5,000
6954392-EL2023-03-21Electrical1400 6TH AVEThis Fire Alarm System TI has six (6) Speaker/strobe devices being adjusted to the new space for strobe coverage. Joint venture with Sequoyah Electric$6,100
6952028-EL2023-03-08Electrical900 UNIVERSITY STProject Renovation for 8-G. The apartment is being renovated and four (4) devices are be taken down and the replaced.$5,000
6935564-EL2023-01-30Electrical4716 RAINIER AVE SAdding a power supply and notification to USPS TI in Columbia City Retail area A. Adding smoke detector above power supply. This is a joint venture between System Solutions and S$20,000
6939606-EL2023-01-30Electrical4568 SAND POINT WAY NETenant Improvement on River A level 4 & 6 to including new initiating, notification devices, power supply and duct detectors. This is a joint venture with VECA and Siemens Industr$50,000
6942619-EL2023-01-13Electrical725 9TH AVE2 smoke detectors and 2 A/V notification devices.$2,500
6935040-EL2023-01-11Electrical201 WESTLAKE AVE NReplacing smoke detectors with heat detectors.$5,000
6904709-EL2023-01-11Electrical1215 E FIR STThis project is a TI on the first floor of the Yesler Housing building and is a daycare/school for young children. The notification in this area is speaker strobes. The school will$18,918
6904703-EL2023-01-11Electrical115 13TH AVEThis project is a new five-story apartment building with horn/strobes notification. The fire system installation will be a joint venture with Kirby Electric, Lake,4/12/2023,address$67,333
6935949-EL2022-11-29Electrical201 16TH AVE EFire alarm panel upgrade in the Main, North, and West buildings. No field devices$57,000
6900594-EL2022-11-22Electrical4800 SAND POINT WAY NEAdding smoke detectors and notification devices to Forest A, Emergency Department Shell area. This is a joint venture with VECA and Siemens.$20,000
6918906-EL2022-11-21Electrical8704 GREENWOOD AVE NInstall a new fire alarm system to meet all applicable codes. The building is mixed-use (Residential, Retail, Parking). The Fire Alarm System includes Smoke Control Pressurization $134,947
6934796-EL2022-11-21Electrical1400 6TH AVEWe are adding six (6) Speaker/Strobe devices to a Restaurant TI in the Sheraton Grande.$6,100
6901446-EL2022-09-30Electrical1500 ALASKAN WAYTHIS PROJECT IS SUBMITTED AS A COMPLETE CODE-COMPLIANT FIRE ALARM SYSTEM WITH SPRINKLER MONITORING AND VOICE NOTIFICATION APPLIANCES, MANUAL AND AUTOMATIC INITIATING DEVICES, AND M$78,670
6921037-EL2022-09-07Electrical714 S CHARLES STThe MXL to Desigo Fire Safety Modular fire alarm migration proposal will consist of the following MXL to Desigo Fire Safety Modular panel conversions, including components and re$19,590
6898886-EL2022-06-29Electrical4800 SAND POINT WAY NEAdding smoke detectors and relays for fire curtain control at Frog elevators. This is a joint venture with Siemens and VECA Electric **Renewed thru Zendesk request, 6/30/2023, EC$15,000
6900640-EL2022-06-29Electrical4800 SAND POINT WAY NEAdding smoke detection and control relays for fire curtains in the Eagle Elevator area of SCH. This is a joint venture with VECA and Siemens. **Renewed thru Zendesk request, 6/30$20,000

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Seattle permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →