COMPANY RECORD · PHILADELPHIA, PA
Rue Electric Inc — permit history in Philadelphia, PA
Rue Electric Inc appears on 57 Philadelphia permit records from 2021 through 2026, all of them electrical.
Permit categories
| Category | Permits | Share |
|---|---|---|
| Electrical | 57 | 100% |
Activity by year
| Year | Permits issued |
|---|---|
| 2021 | 6 |
| 2022 | 14 |
| 2023 | 14 |
| 2024 | 10 |
| 2025 | 6 |
| 2026 | 7 |
Busiest year on record: 2022, with 14 permits. One project can account for several filings, so read this as filing activity rather than workload.
PROJECTS AHEAD SEARCH
Search every Philadelphia permit, not only this company's
This page is a snapshot of Rue Electric Inc. The search behind it holds more than 242,223 Philadelphia permits naming a contractor, since 2021: 82,008 plumbing permits, 51,127 electrical permits, 25,710 mechanical permits, 25,367 residential building permits, 24,512 zoning permits.
- Search the full history by company, address, permit type or date range.
- Set an alert and get an email when a new permit matches — the next permit Rue Electric Inc files, or any new electrical permit in Philadelphia. A new permit is an early signal of work to bid on, supply or finance.
- Export to CSV for your CRM or spreadsheet.
Free account: newest 7 days of records, 10 searches a day and 1 daily alert. Full history, CSV export and instant alerts on paid plans from $49 a month ($24.50 for the first 3 months). Compare plans
Names on the same project timelines
| Name in source | Linked permits | Last seen |
|---|---|---|
| Aaron Weiner Construction Inc | 8 | 2023-09-05 |
| Domus, Inc. | 5 | 2025-09-03 |
| Bsi Construction LLC | 4 | 2024-05-21 |
| Mcdonald Building Co LLC | 3 | 2025-06-23 |
| National Maint & Build Out LLC | 2 | 2025-04-23 |
| Shawmut Woodworking & Supply Inc | 2 | 2026-02-26 |
| Dale Corporation | 2 | 2026-01-14 |
| Camfred Construction LLC | 1 | 2022-08-01 |
| Deracon LLC | 1 | 2023-09-29 |
| Daniel J. Keating Company | 1 | 2023-05-23 |
| B. Tait Builders, LLC. | 1 | 2024-05-29 |
| Jb Richards Construction LLC | 1 | 2023-04-01 |
16 named participants share a resolved project timeline with Rue Electric Inc. A shared timeline is a research lead, not proof of a partnership or a current contract. Names appear as the authority published them.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 2411 N 11TH ST | 2026-10-24 |
| 3319 EDGEMONT ST | 2026-08-11 |
| 6232-50 WALNUT ST | 2026-08-04 |
| 2079 N 63RD ST | 2026-04-30 |
| 2201 E TIOGA ST | 2026-04-03 |
| 1608-34 SANSOM ST | 2026-02-26 |
| 2190 HORNIG RD | 2026-01-14 |
| 226 N HOBART ST | 2025-08-07 |
| 3400 W GIRARD AVE | 2025-06-23 |
| 641 LINDLEY AVE | 2025-05-07 |
| 2760 RED LION RD | 2025-04-23 |
| 6441 LANSDOWNE AVE | 2024-12-07 |
| 606-22 SPRING GARDEN ST | 2024-10-28 |
| 2112 RIDGE AVE | 2024-09-13 |
38 distinct addresses on record; the 14 most recent are shown. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Also named on permits at the same addresses
| Company | Shared addresses | Years |
|---|---|---|
| Tandem Associates Inc | 10 | 2021–2026 |
| Preferred Fire Protection Inc | 8 | 2021–2025 |
| Oneida Fire Protection Inc | 4 | 2022–2026 |
| Joseph Rosati Inc | 4 | 2023–2026 |
| Mk Fire Protection & Supply, LLC | 4 | 2021–2026 |
| Churchville Mechanical Inc | 4 | 2021–2026 |
| Domus, Inc. | 4 | 2022–2026 |
| Klehr Harrison Harvey Branzburg LLP | 4 | 2021–2025 |
Companies that also appear in Philadelphia permit records at addresses where Rue Electric Inc filed, in any year. Sharing an address is a documented co-appearance, not proof that they worked on the same project or with each other.
Permits on record
57 permits; open the 50 most recent
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| EP-2026-005463 | 2026-10-24 | Electrical | 2411 N 11TH ST | Installation of incoming HT service for building Installation of Switchgear and multiple sub panels for branch circuits, apartment feeder panels Installation of Fire alarm ,Fire Pu | |
| EP-2026-007370 | 2026-08-11 | Electrical | 3319 EDGEMONT ST | Install a new dedicated circuit off of the existing panel for a new AC unit Install a new 2 pole 25 amp breaker and feed AC unit with a disconnect | |
| EP-2026-001439 | 2026-08-04 | Electrical | 6232-50 WALNUT ST | Install 18 new 225-amp panels in the basement, fed from the existing switchgear Install 6 new panels for the new HVAC throughout the building Install new branch circuits for each a | |
| EP-2026-002363 | 2026-04-30 | Electrical | 2079 N 63RD ST | Install new 125 amp panel for DOAS system Install new lighting and power branch circuits as per drawings Fire alarm is existing and will be relocated to meet code | |
| EP-2026-000606 | 2026-04-03 | Electrical | 2201 E TIOGA ST | Provide new incoming service for residential units (1600 amp) and 1000 amp for the rest of the building. Install all branch circuits for power and lighting. Install tel/CATV and | |
| EP-2026-000608 | 2026-02-26 | Electrical | 1608-34 SANSOM ST | Install one new 225-amp panelboard fed from the existing switchgear. Provide new branch circuits utilizing MC cable in accordance with approved drawings. Install CAT 6 cabling for | |
| EP-2025-011203 | 2026-01-14 | Electrical | 2190 HORNIG RD | Relocate 2 electrical panels as per drawings Install new 60 amp panel as per drawings Install fire alarm as per attached drawings Install all branch circuits and lighting as per dr | |
| EP-2025-008432 | 2025-09-03 | Electrical | 2201 E TIOGA ST | Install new 200 amp panel for jobsite temp. power. Install power feed for job site trailer | |
| EP-2025-006838 | 2025-08-07 | Electrical | 226 N HOBART ST | Upgrade service from 100 amp to 200 amp Install new service cable, new meter socket, and new panel | |
| EP-2025-005844 | 2025-06-23 | Electrical | 3400 W GIRARD AVE | Install a total of 14 lights in 2 bathrooms. Install 2 floor boxes and 6 receptacles in meeting room. All circuits shall come from existing panels Install wiring for 3 exhaust fans | |
| EP-2025-003847 | 2025-06-03 | Electrical | 1608-34 SANSOM ST | Install new 400 amp 480 volt panel with a transformer and 2 sub panels 120/208 volt. Install all branch circuits from new panels. Install lighting and power per plans. Install fire | |
| EP-2025-003497 | 2025-05-07 | Electrical | 641 LINDLEY AVE | INSTALL 1000 AMP ELECTRICAL SERVICE, METER SOCKET AND CIRCUIT BREAKER PANEL WITH PROPER GROUNDING AND BONDING. INSTALL LIGHTING, SWITCHES AND RECEPTACLE OUTLETS. INSTALL DEDICAAT | |
| EP-2025-001578 | 2025-04-23 | Electrical | 2760 RED LION RD | Electrical Permit for combo CP-2024-006425 | |
| EP-2024-011511 | 2024-12-19 | Electrical | 641 LINDLEY AVE | Install 1 200 amp service for temporary power and lighting for construction site. Hook up job trailer | |
| EP-2024-008536 | 2024-12-07 | Electrical | 6441 LANSDOWNE AVE | INSTALL A 1,800 AMP 120/208V 3 PHASE SERVICE & 1,800 AMP SWITCHBOARD. INSTALL (2) 400 AMP FEEDERS & METER BANKS, (1) 300 AMP FEEDER & METER BANK. INSTALL PANELS, FEEDERS, & TRANSFO | |
| EP-2024-010908 | 2024-11-28 | Electrical | 3400 W GIRARD AVE | Install 1 new panel 200 amp 3 phase MCB Install lighting as per drawings Install as per 2017 NEC | |
| EP-2024-009472 | 2024-10-28 | Electrical | 606-22 SPRING GARDEN ST | Electrical Permit for combo CP-2024-001527 | |
| EP-2024-004516 | 2024-09-13 | Electrical | 2112 RIDGE AVE | Install 400 amp incoming service for fire pump, 800 amp for MDP, and 1200 amp for residential and commercial metering. Install all grounding. Install all branch circuits for pow | |
| EP-2024-006516 | 2024-07-09 | Electrical | 6441 LANSDOWNE AVE | Temporary 200 amp service for job trailer and temp power for construction site | |
| EP-2024-005276 | 2024-06-04 | Electrical | 7159 JAMES ST | Install 200 amp service Aerial | |
| EP-2023-008476 | 2024-05-29 | Electrical | 2327-83 COTTMAN AVE | INSTALL FIRE ALARM SYSTEM ACCORDING TO THE 2017 NEC, 2016 NFPA 72 AND PER PLANS. | |
| EP-2024-004219 | 2024-05-21 | Electrical | 3301 SOLLY AVE | Install 2- 800 amp disconnects for service to building, to include 2- 400 amp future panels. Install all branch circuits for power and lighting as per plans. Install power only for | |
| EP-2023-009880 | 2024-02-23 | Electrical | 217 N 9TH ST | INSTALL A 800 AMP/120/208V/ 3 PHASE MDP, (2) 800 AMP 120/208V/ 3 PHASE METER BANKS. INSTALL A 208V/ 3 PHASE SERVICE FOR THE FIRE PUMP. INSTALL A 100 KW GENERATOR & (2) ATS, INSTALL | |
| EP-2023-010447 | 2023-11-14 | Electrical | 2604 ISLAND AVE | We will be doing the incoming service ONLY!! Install PECO vault for transformer. Install 6- 4" PVC conduits for 1200 amp service to a CT cabinet for a distribution panel. Install | |
| EP-2023-005555 | 2023-10-13 | Electrical | 5364 JACKSON ST | Install all incoming service from existing gear in original building, into our new service, as per drawings. Install fire alarm system as per plans. Purchase and install all lighti | |
| EP-2023-004081 | 2023-09-29 | Electrical | 6800 ESSINGTON AVE | Electrical Permit for combo CP-2022-006908 | |
| EP-2023-007956 | 2023-09-05 | Electrical | 1909 WALNUT ST | Install appliances off of existing power in Unit We are ONLY installing the appliances and plugging in place | |
| EP-2023-008035 | 2023-08-25 | Electrical | 217 N 9TH ST | Install 100 amp temporary service for construction site and hook up 1 job trailer AS PER NEC 2017 | |
| EP-2023-006765 | 2023-07-24 | Electrical | 1909 WALNUT ST | Install all branch circuits as per drawings for unit 4402 Installation to include power and lighting, switches and receptacles. Install power for Lutron lighting system as per 2017 | |
| EP-2023-004662 | 2023-06-13 | Electrical | 1909 WALNUT ST | Install branch circuits for lighting and power off of existing panel installed by others. Install all final electrical devices such as switches and receptacles . ALL WORK IS TO BE | |
| EP-2023-004734 | 2023-05-23 | Electrical | 2112 RIDGE AVE | Install 200 amp service for trailer and job site power and lighting as used for temporary during construction as per 2017 nec | |
| EP-2023-002603 | 2023-04-20 | Electrical | 1909 WALNUT ST | Install all branch circuits as per drawings. This will include all switches, lights, and receptacles. Install power to Lutron lighting panels AS PER 2017 NEC | |
| EP-2022-009876 | 2023-04-01 | Electrical | 12002 E ROOSEVELT BLVD | INSTALL (2) 400 AMP 120/208V 3 PHASE SERVICES, (1) CT CABINET & METERING, (1) 400 AMP SERVICE RATED ENCLOSED CIRCUIT BREAKER, (1) 400 AMP FEEDER TO TENANT SHELL SPACE FOR FUTURE FI | |
| EP-2023-000712 | 2023-04-01 | Electrical | 2201 E ALLEGHENY AVE | Install all incoming power and raceways as per drawings. Install all lighting and switching ,fire pump and controls as per drawings Install owner provided generator and all associa | |
| EP-2023-002599 | 2023-04-01 | Electrical | 1909 WALNUT ST | Install all branch circuits including switches, lights, and receptacles as per drawings. Install sub panel off of existing panel in the unit as per 2017 nec | |
| EP-2022-009875 | 2023-04-01 | Electrical | 12000 E ROOSEVELT BLVD | Install electrical service to building to include from PECO PAD-MOUNT a 400 amp, 800 amp, and a 1200 amp service for future tenants. Install lighting for code, and wiring for roof | |
| EP-2022-012886 | 2023-02-09 | Electrical | 1909 WALNUT ST | Install power branch circuits and lighting branch circuits as per drawings. Install 110 volt smoke alarms per code. Install telephone, data, and CATV wiring as per 2017 NEC. | |
| EP-2022-011980 | 2022-12-20 | Electrical | 3000 ISLAND AVE | INSTALL AN ADDRESSABLE FIRE ALARM SYSTEM . ALL WORK IN ACCORDANCE WITH THE 2017 NEC & 2016 NFPA-72. | |
| EP-2022-011287 | 2022-11-29 | Electrical | 45 N 3RD ST | Install branch circuits for lighting and power utilizing existing panels. Install new panel PC utilizing existing panel P1 to feed the basement branch circuits. Install all swi | |
| EP-2022-009997 | 2022-11-28 | Electrical | 801 E ERIE AVE | Install all branch circuits for lighting and receptacles as per plans. All circuits will be installed using the existing panels and breakers Install low voltage wiring for tel/Data | |
| EP-2022-006508 | 2022-11-23 | Electrical | 1611-41 RUAN ST | Install a 1,200 amp service, (44) gang meter bank, (44) 100 amp panels & feeders. Install a 800 amp service & MDP, (2) 200 amp panels & feeders, (2) 100 amp panels & feeders. Provi | |
| EP-2022-011334 | 2022-11-16 | Electrical | 45 N 3RD ST | Rough-In Permit for EP-2022-011287 Install branch circuits for lighting and power off of existing panels. Install new panel PC off of existing panel P1 to feed the basement branch | |
| EP-2022-005619 | 2022-11-04 | Electrical | 3000 ISLAND AVE | Electrical Permit for combo CP-2021-009493 **SEPARATE FIRE ALARM PERMIT REQ'D** | |
| EP-2022-006504 | 2022-09-08 | Electrical | 1909 WALNUT ST | Install electrical systems to entire floor as per drawings. Install additional fire alarm . Install new 400 amp panel for power and lighting. Install switches, receptacles, lights, | |
| EP-2022-006510 | 2022-08-01 | Electrical | 3801-51 LOCUST WALK | Remove old wiring from walls being removed. Remove existing lights, switches, and receptacles and relocate in new walls as per plans and 2017 NEC. Install new duct detectors as pe | |
| EP-2022-007296 | 2022-07-25 | Electrical | 425-29 CHESTNUT ST | Demo 4 existing lights and replace with 8 LED hi hats using existing circuit. Install 2 floor boxes in new part of stage. Remove existing receptacles and boxes and replace with new | |
| EP-2022-007132 | 2022-07-19 | Electrical | 12427 SWEET BRIAR RD | Install new 200 amp service as per 2014 nec | |
| EP-2022-007130 | 2022-07-19 | Electrical | 2034 S DARIEN ST | Install 28 switches, 34 lights, and 62 receptacles using the existing service and breakers. Install telephone and CATV Install 110 volt smoke detectors as per 2014 nec AMEND Chang | |
| EP-2022-004020 | 2022-05-27 | Electrical | 4301 BYBERRY RD | Remove Electrical boxes and outlets for new cash wrap furniture and replace using existing wiring. Install 1 power pole for soda case using existing circuit as per 2017 nec | |
| EP-2022-004031 | 2022-04-28 | Electrical | 1611-41 RUAN ST | Install 200Amp panel for temporary power for construction site as per 2017 nec |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Source and limits
Public Philadelphia permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →
Is this your company? Show this public permit record on your website with a free badge.