COMPANY RECORD · NEW YORK, NY
Deborah Bradley Cons & Mg — permit history in New York, NY
Deborah Bradley Cons & Mg appears on 49 New York permit records from 2020 through 2026, most often general construction (95.9% of the record).
Permit categories
| Category | Permits | Share |
|---|---|---|
| General construction | 47 | 95.9% |
| Mechanical / HVAC | 2 | 4.1% |
2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.
Activity by year
| Year | Permits issued |
|---|---|
| 2020 | 1 |
| 2021 | 14 |
| 2022 | 6 |
| 2023 | 5 |
| 2024 | 3 |
| 2025 | 11 |
| 2026 | 9 |
Busiest year on record: 2021, with 14 permits. One project can account for several filings, so read this as filing activity rather than workload.
Named on the same permit
| Name in source | Linked permits | Last seen |
|---|---|---|
| Panili Plumbing & Htg LLC | 1 | 2025-10-30 |
1 companies are named alongside Deborah Bradley Cons & Mg on the same New York permit. A shared permit is a documented co-appearance, not proof of a current contract. Names appear as the authority published them.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 441 EAST FORDHAM ROAD | 2026-08-06 |
| 181-07 JAMAICA AVENUE | 2026-08-04 |
| 181-11 JAMAICA AVENUE | 2026-08-04 |
| 63 FLUSHING AVENUE | 2026-05-12 |
| 395 DEKALB AVENUE | 2026-04-23 |
| 4452 PARK AVENUE | 2026-02-18 |
| 4448 PARK AVENUE | 2026-02-17 |
| 153-49 61 ROAD | 2026-01-07 |
| 119-05 LINDEN BOULEVARD | 2025-11-24 |
| 300 EAST 115 STREET | 2025-10-24 |
| 119-03 LINDEN BOULEVARD | 2025-09-30 |
| 730 BRYANT AVENUE | 2024-08-13 |
| 75 RICHMOND TERRACE | 2024-06-05 |
| 15 WORTH STREET | 2024-05-15 |
36 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $16,040 to $34,999,860, median $135,000. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Permits on record
49 permits; open the full list
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| X01424089-I1-GC | 2026-08-06 | General construction | 441 EAST FORDHAM ROAD | INSTALLATION OF STORMWATER MANAGEMENT SYSTEM (SUBSURFACE INFILTRATION TANKS) PER DEP PRIVATE PROPERTY GREEN INFRASTRUCTURE RETROFIT INCENTIVE PROGRAM. NO CHANGE TO USE, EGRESS, OR | $700,000 |
| Q01129143-I1-GC | 2026-08-04 | General construction | 181-07 JAMAICA AVENUE | PROPOSED EESE TAX ABATEMENT FOR INSTALLATION OF UNENCLOSED NON-ACCESSORY ENERGY STORAGE SYSTEM WITH ASSOCIATED EQUIPMENT FILED IN CONJUNCTION WITH Q01129003-I1 | $575,000 |
| Q01124174-I1-GC | 2026-08-04 | General construction | 181-11 JAMAICA AVENUE | PROPOSED EESE TAX ABATEMENT OF UNENCLOSED NON-ACCESSORY ENERGY STORAGE SYSTEM WITH ASSOCIATED EQUIPMENT FILED IN CONJUNCTION WITH Q01124144 | $575,000 |
| B00994105-S1-MS | 2026-05-12 | Mechanical / HVAC | 63 FLUSHING AVENUE | Building 275:TO REMOVE AND REPLACE THE EXISTING ELECTRICAL EQUIPMENT IN THE CURRENT ROOM TO A HIGHER PLATFORMELEVATION IN THE SAME ROOM (replace exhaust fan-new louver-replace elec | $60,000 |
| B00994105-I1-GC | 2026-05-11 | General construction | 63 FLUSHING AVENUE | Building 275: TO REMOVE AND REPLACE THE EXISTING ELECTRICAL EQUIPMENT IN THE CURRENT ROOM TO A HIGHER PLATFORMELEVATION IN THE SAME ROOM(replace door and install steel platform) | $40,000 |
| B01356204-I1-GC | 2026-04-23 | General construction | 395 DEKALB AVENUE | INSTALLATION OF STORMWATER MANAGEMENT SYSTEM (SUBSURFACE INFILTRATION TANKS) PER DEP PRIVATE PROPERTY GREEN INFRASTRUCTURE RETROFIT INCENTIVE PROGRAM. NO CHANGE TO USE, EGRESS, OR | $600,000 |
| X01192287-I1-GC-CX | 2026-02-18 | General construction | 4452 PARK AVENUE | General construction and structural modifications as per plans filed herewith. No change to use, occupancy, or egress. Related applications are AltCO #X01171133-I1 , and EESE X011 | $125,102 |
| X01284047-I1-GC-CX | 2026-02-17 | General construction | 4448 PARK AVENUE | General construction and structural modifications as per plans filed herewith. No change to use, occupancy, or egress. Related applications are ALTCO # X01214138-I1 , and EESE # X | $125,102 |
| Q01327822-I1-GC | 2026-01-07 | General construction | 153-49 61 ROAD | INSTALLATION OF STORMWATER MANAGEMENT SYSTEM (SUBSURFACE INFILTRATION TANKS) PER DEP PRIVATE PROPERTY GREEN INFRASTRUCTURE RETROFIT INCENTIVE PROGRAM. NO CHANGE TO USE, EGRESS, OR | $750,000 |
| Q00951276-I1-GC | 2025-11-24 | General construction | 119-05 LINDEN BOULEVARD | Proposed Battery Energy Storage Systems with accessory equipment and concrete pads. ESS TAX | $1,000,000 |
| M00853523-S1-GC | 2025-10-24 | General construction | 300 EAST 115 STREET | General construction, site-work related to work for the storm and drainage piping infrastructure to improve management of stormwater runoff from the tributary impervious surfaces. | $493,000 |
| Q00951263-I1-GC | 2025-09-30 | General construction | 119-03 LINDEN BOULEVARD | Proposed new battery energy storage system with accessory equipment with concrete pads. ESS Tax | $1,000,000 |
| Q01124144-S2-GC | 2025-09-12 | General construction | 181-11 JAMAICA AVENUE | INSTALLATION OF STEEL FRAME; POSTS & BEAMS FOR BATTERY ENERGY STORAGE SYSTEMS | $135,000 |
| Q01129003-S1-GC | 2025-08-29 | General construction | 181-07 JAMAICA AVENUE | INSTALLATION OF STEEL FRAME; POSTS & BEAMS FOR BATTERY ENERGY STORAGE SYSTEMS | $135,000 |
| Q01182342-I1-GC | 2025-07-24 | General construction | 181-07 JAMAICA AVENUE | INSTALLATION OF CONCRETE PADS AND PRIVACY FENCE. FILED IN CONJUNCTION WITH Q01129003 | $285,600 |
| Q01182343-I1-GC | 2025-07-17 | General construction | 181-11 JAMAICA AVENUE | INSTALLATION OF CONCRETE PADS AND PRIVACY FENCE. FILED IN CONJUNCTION WITH Q01124144 | $285,640 |
| Q00951263-S1-GC-CX | 2025-03-26 | General construction | 119-03 LINDEN BOULEVARD | Installation of concrete pads for battery energy storage systems | $150,000 |
| Q00951276-S1-GC-CX | 2025-03-26 | General construction | 119-05 LINDEN BOULEVARD | Installation of concrete pads for battery energy storage systems. | $150,000 |
| Q01107523-I1-GC | 2025-01-07 | General construction | 119-05 LINDEN BOULEVARD | SITE PREPARATION, INSTALLATION OF CONCRETE PADS AND PRIVACY FENCE. NO CHANGE TO OCCUPANCY, USE OR EGRESS FILED IN CONJUNCTION WITH 119-03 LINDEN BLVD Q01107433. | $200,000 |
| Q01107433-I1-GC | 2025-01-07 | General construction | 119-03 LINDEN BOULEVARD | INSTALLATION OF CONCRETE PADS AND PRIVACY FENCE. FILED IN CONJUNCTION WITH 119-05 Q01107523 | $200,000 |
| X00757391-I1-GC-CX | 2024-08-13 | General construction | 730 BRYANT AVENUE | herewith filing for Structural installation for slab and retaining wall for new battery storage in MS.424 | $465,000 |
| S00916257-I1-GC | 2024-06-05 | General construction | 75 RICHMOND TERRACE | 75 RICHMOND TERRACE - GENERAL CONSTRUCTION INCLUDING REPAIRS TO THE 9/11 MEMORIAL SITE. WORK INCLUDES REPAIRING DAMAGED CONCRETE AND GRANITE PAVERS, RESETTING BOLLARDS THROUGHOUT. | $250,000 |
| M01033292-I1-GC | 2024-05-15 | General construction | 15 WORTH STREET | Temp Placement of 2 modified 8'x20' modular containers to include coiling door for deliveries.Units will take up 4 parking spaces in parking lot. Temporary wooden deck between the | $16,040 |
| X00757312-I1-GC-CX | 2023-09-01 | General construction | 1290 SPOFFORD AVENUE | Structural modifications for P.S. 48 | $2,666,318 |
| Q00729712-I1-GC-CX | 2023-02-09 | General construction | 31-01 20 AVENUE | Proposed earthwork and civil site preparation for existing LNG plant upgrade as per plan. No change of use, egress or occupancy. | $3,633,900 |
| M00476128-I1-GC | 2023-01-19 | General construction | 1901 FIRST AVENUE | Filed herewith civil work as shown on drawings. Underground plumbing filed separately under DOB NOW # M00476136. No change in use, egress or occupancy. | $34,999,860 |
| B00447947-I1-EA | 2023-01-17 | General construction | 375 CENTRAL AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $91,140 |
| B00446469-I1-EA | 2023-01-17 | General construction | 172 MENAHAN STREET | The work includes the installation of a subsurface storage system used to collect stormwater runoff from impervious areas and infiltrate it into the ground. The proposed system wil | $70,850 |
| B00447946-I1-EA | 2022-09-09 | General construction | 440 CENTRAL AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $37,552 |
| B00447948-I1-EA | 2022-07-14 | General construction | 200 PALMETTO STREET | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $77,850 |
| Q00657401-I1-GC-CX | 2022-06-06 | General construction | 22-11 39 AVENUE | Installation of new firewall, transformer bus supports, transformer concrete moats, and associated steel framing at Con Edison's Queensbridge Substation. | $1,200,000 |
| M00622519-I1-GC | 2022-04-04 | General construction | 110 ANDES ROAD | INTERIOR ALTERATIONS OF EXISTING GROUND FLOOR SPACE TO INCLUDE MINOR DEMOLITION AND CONSTRUCTION OF IT ROOM AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS U | $100,000 |
| B00447946-I1-GC | 2022-01-28 | General construction | 440 CENTRAL AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $37,552 |
| B00446947-I1-GC-CX | 2022-01-10 | General construction | 524 KNICKERBOCKER AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $104,680 |
| B00446469-I1-GC | 2021-10-20 | General construction | 172 MENAHAN STREET | The work includes the installation of a subsurface storage system used to collect stormwater runoff from impervious areas and infiltrate it into the ground. The proposed system wil | $70,850 |
| B00447947-I1-GC | 2021-10-20 | General construction | 375 CENTRAL AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $91,140 |
| B00447948-I1-GC | 2021-10-20 | General construction | 200 PALMETTO STREET | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $77,850 |
| B00502674-I1-GC | 2021-09-24 | General construction | 95 GLENMORE AVENUE | The proposed work will manage stormwater runoff on the property through the use of an underground storage system located under the basketball court in Howard Playground. General co | $353,446 |
| B00447943-I1-GC-CX | 2021-09-15 | General construction | 415 EVERGREEN AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $44,678 |
| B00447944-I1-GC-CX | 2021-09-09 | General construction | 1240 GATES AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $118,490 |
| B00447939-I1-GC-CX | 2021-08-20 | General construction | 357 WILSON AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $108,850 |
| B00498192-I1-GC | 2021-08-04 | General construction | 125 CENTRAL AVENUE | General Construction work for a proposed subsurface retention system green infrastructure practice. | $122,642 |
| B00516795-I1-GC | 2021-08-03 | General construction | 9101 DITMAS AVENUE | INSTALLATION OF STORMWATER MANAGEMENT SYSTEM (SUBSURFACE RETENTION) PER DEP ON-SITE PUBLIC PROPERTY GREEN INFRASTRUCTURE RETROFIT CONTRACT, NO CHANGE TO USE, EGRESS OR OCCUPANCY. | $173,000 |
| B00498321-I1-GC | 2021-08-02 | General construction | 64 IRVING AVENUE | Maria Hermandez Park Playground - Proposed General Construction for Subsurface Bio retention/Rain Garden system green infrastructure practice. No change in use egress or occupancy. | $110,573 |
| B00447942-I1-GC-CX | 2021-07-20 | General construction | 310 CENTRAL AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $34,306 |
| B00447941-I1-GC-CX | 2021-07-19 | General construction | 580 CENTRAL AVENUE | General construction activities for the installation of an underground stormwater storage and associated piping and inlets. Area of excavation is in the parking lot of the building | $42,908 |
| B00487389-I1-GC | 2021-06-14 | General construction | 334 SUTTER AVENUE | Project involves the installation of on site storm water drainage retention systems. The systems use underground chambers and a rain garden to temporarily store flow in accordance | $321,000 |
| B00487371-I1-GC | 2021-06-14 | General construction | 430 DUMONT AVENUE | Project involves the installation of on site storm water drainage retention systems. The systems useunderground chambers to temporarily store flow in accordance with the nyc dep gr | $228,000 |
| M00368647-I1-MS | 2020-07-24 | Mechanical / HVAC | 2238 5 AVENUE | Install temporary generator at OSP as per plans. No change in use, egress, or occupancy. | $25,000 |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Source and limits
Public New York permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →