COMPANY RECORD · SEATTLE, WA

Valley Electric — permit history in Seattle, WA

Valley Electric appears on 76 Seattle permit records from 2018 through 2026, all of them electrical.

Permit categories

CategoryPermitsShare
Electrical76100%

Activity by year

YearPermits issued
20186
201919
20208
20212
202212
20237
202410
20258
20264

Busiest year on record: 2019, with 19 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
1959 NE PACIFIC ST2026-07-22
2034 NE SKAGIT LN2026-06-08
4800 S HENDERSON ST2026-04-28
1550 N 115TH ST2026-01-22
615 WESTLAKE AVE N2025-09-25
1012 SW TRENTON ST2025-08-18
12970R 5TH AVE NE2025-03-04
8815 SEWARD PARK AVE S2025-02-04
1730 MINOR AVE2025-01-16
1100 OLIVE WAY2025-01-09
5500 RAINIER AVE S2024-08-27
2445 3RD AVE S2024-08-09
2221 ALASKAN WAY2024-05-10
100 S KING ST2024-04-30

44 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $16,688,268, median $21,000. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

76 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
7138466-EL2026-07-22Electrical1959 NE PACIFIC STINTERIOR RENOVATION OF TWO PROCEDURE ROOMS TOTALING APPROXIMATELY 620 SQUARE FEET ON LEVEL THREE OF THE EXISTING SURGERY PAVILION. NORA Building Permit 7134676-CN [7/13/2026$227,000
7139995-EL2026-06-08Electrical2034 NE SKAGIT LNART AND MUSIC RENO [5/11/26 KEF - Plan set conditionally approved pending assignment of an EC and issuance of the building permit (7096624-CN)] [6/8/26 KEF - EC assigned, building $1,001,657
7140384-EL2026-04-28Electrical4800 S HENDERSON STBuilding fire alarm tenant improvement. Add new relay module to shutdown audio visual equipment. Building monitored with existing AES wireless communicator$2,920
7117877-EL2026-01-22Electrical1550 N 115TH STE-WING 6 PATIENT ROOM$55,000
7099212-EL2025-09-25Electrical615 WESTLAKE AVE NWe are installing (14) speaker/strobes.$8,431
7102168-EL2025-08-18Electrical1012 SW TRENTON STProvide telecommunications cabling for the schools security cameras, classroom projectors, and intercom system. PowerCom job 451792-01$86,933
7101980-EL2025-08-15Electrical1012 SW TRENTON STWe are installing (1) control relay as a joint venture with Valley Electric.$5,918
7069526-EL2025-04-23Electrical1959 NE PACIFIC STInterior Remodel of 1.300sf of existing inpatient hospital space to accept a new linear accelerator. Work will include selective demolition and new construction. New lighting wi$523,613
7073468-EL2025-03-04Electrical12970R 5TH AVE NEInstallation of a metered service at the intersection of 5th Avenue NE and NE 130 ST. 2/20/2026 Renewal requested through Zendesk [C.Kenefick 8/19/2026 - Fees adjusted to reflect t$8,000
6990740-EL2025-02-04Electrical8815 SEWARD PARK AVE SInstalling fire alarm system, Security Solutions NW is parts and smarts, Joint venture with Valley Electric who is doing the install$180,000
7065558-EL2025-01-16Electrical1730 MINOR AVETenant improvement for the 13th Floor of Met Park East. A speaker/strobe is being added to the mailroom and connected to existing circuits.$5,482
7064236-EL2025-01-09Electrical1100 OLIVE WAYAdd speaker strobe to 2 new phone booths.$2,200
7042887-EL2024-08-27Electrical5500 RAINIER AVE SApproximately 1,000 sq ft tenant improvement, small office with new receptacles and lighting$22,000
7031984-EL2024-08-09Electrical2445 3RD AVE S8-9-24 BZ Job Contact Nick Clayton 425-870-6815. Final phase of electrical work for replacement switchboard from 2023 water damage.$250,000
6999139-EL2024-05-29Electrical1550 N 115TH STRenovation to create new IR lab, offices, and data closet.[ 6-12-25 BZ VALLEY ELEC CO OF MTVERNON INC; New Electrical Contractor as Primary per permit owners request]$650,000
6981669-EL2024-05-10Electrical2221 ALASKAN WAYThe project includes new SCL service equipment being installed on Pier 66 to provide power to cruise ships. This service will be fed via Terminal 46 where SCL power will be sourced$4,500,000
7022191-EL2024-04-30Electrical100 S KING STInstallation of 17.1 kWdc roof mounter photovoltaci power generating system. Primary components are (38) LG 450 Watt panels & (10) AP Systems QT2 Quad 208v microinverters.[04/30/24$2,200
7019985-EL2024-04-18Electrical2445 3RD AVE SInstallation of a temporary 800A switchboard to support the kitchen remodel at the Stanford Center. If you have an questions or need any additional information, please contact Nick$125,000
7010625-EL2024-03-11Electrical1201 E UNION STInstalling fire alarm system to Seattle Academy. Joint venture for Security Solutions and Valley Electric. 4/4/2025 jnl renewal$80,000
7008898-EL2024-02-09Electrical13303 5TH AVE NEInstall Temporary power for job site trailers$15,000
7007894-EL2024-02-05Electrical13001 5TH AVE NERe-route power for WSDOT Cabinet and Camera conduit to light pole.$38,000
6997211-EL2024-01-04Electrical1550 N 115TH STLevel 1 Renovation of IR lab$49,000
7000683-EL2023-12-22Electrical801 ALASKAN WAYNew Fire Alarm Panel. 6 notification devices, 4 initiating devices.$60,000
6999531-EL2023-12-06Electrical13110 5TH AVE NEGet started permit to allow for platform bonding installation$10,000
6983356-EL2023-09-18Electrical401 ELLIOTT AVE WA management office < 1,500 sq. ft. is being added to the project under the #6888021-EL 401 Elliott Ave W electrical permit on Level 1. This scope of work includes new branch circu$85,197
6984533-EL2023-09-06Electrical401 ELLIOTT AVE WAdded 6 notification devices to cover office layout.$6,000
6953530-EL2023-03-30Electrical2445 3RD AVE SFire main line broke, flooded one of the main electrical rooms, and ruined the main switchboard; proposed temporary work while new switchboard is being ordered. 3/23/23 JSS See 695$500,000
6950966-EL2023-03-23Electrical2445 3RD AVE SProvide 2- 800kw and 1-500kw generators, 5 distribution panel boards and 20+ thousand feet of type W temporary cabling with cam locks to provide temp power back up for the John Sta$1,000,000
6944364-EL2023-01-24Electrical901 FAIRVIEW AVE NThis project will be completed in 3 phases, each needing their own inspection so that we can energize the pedestals upon completing each phase. INSTALL (21) SHORE POWER PEDESTALS W$200,000
6930782-EL2022-10-31Electrical905 NE 45TH STOn the exterior wall of stairwell B at the rooftop there is an existing exterior receptacle. Valley Electric will be extending this circuit approximately 25' and installing (1) du$500
6903833-EL2022-10-24Electrical801 ALASKAN WAYAdding Fire Alarm Panel and devices for Colman Dock - VPAC Building.$10,000
6926296-EL2022-10-05Electrical520 PIKE ST3,500 sq ft office interior expansion FA system, TI, adding 13 devices$100
6925607-EL2022-09-30Electrical520 PIKE STLighting remodel including demolition of existing fixtures. Valley Electric installed 47 new fixtures and 5 exit signs within this space.$100
6914362-EL2022-08-01Electrical520 PIKE ST3,500 sq ft office interior expansion including power and lighting.$65,000
6913408-EL2022-07-26Electrical548 1ST AVE SWSDOT fleet vehicle storage facility$437,391
6903830-EL2022-06-30Electrical1101 8TH AVEInstall (24) Tesla Gen3 wall connector charging stations related to previously approved infrastructure under electrical permit 6879962-EL reviewed by David Rankin. Updated parkin$16,000
6899291-EL2022-05-11Electrical1101 8TH AVEAdding a hard lid ceiling in the level 1 egress passageway E116. Includes lowering (4) existing FA speaker devices into hard lid.$15,000
6879962-EL2022-03-14Electrical1101 8TH AVEProvisions for 110 electric vehicle charging stations with power monitoring software. D.R was our original reviewer on this project. 3-14-22 DR PLANS APPROVED AND PERMIT ISSUED$400,000
6878929-EL2022-02-08Electrical1111 EXPEDIA GROUP WAY WApproximately 13,000 sq ft tenant improvement of the building J drum area which will include conference areas, private offices and a small kitchenette.$889,205
6863286-EL2022-02-02Electrical1400 NW 53RD STInstallation of an Emergency Alarm System as required under Section 908 of the Seattle BC and a H-3 occupancy. **Renewed per Zendesk request, 1/4/23, EC**$4,650
6870745-EL2022-01-27Electrical11725 1ST AVE NEADD FIRE ALARM SYSTEM AND DEVICES. JOINT VENTURE BETWEEN ADT COMMERCIAL AND VALLEY ELECTRIC. 1/4/2023 CG Renewed permit$0
6826346-EL2021-04-30Electrical6760 34TH AVE SWThis project includes a two story classroom addition, entry addition, limited site improvements, and limited remodeling of the existing building. The existing 2000A main switchboar$2,091,210
6821348-EL2021-01-29Electrical1111 EXPEDIA GROUP WAY WAdding linear lighting to the existing linear lighting around the water feature collar.$40,000
6795751-EL2020-11-05Electrical1530 N 115TH STAdd significant additional detection and notification in sprinkled building.$15,000
6802845-EL2020-09-28Electrical1550 N 115TH STModifications to existing fire alarm system for tenant improvement: NW Hospital E-wing sleep rooms.$2,000
6795292-EL2020-08-10Electrical1201 ALASKAN WAYAdding a relay to a fire alarm system using existing circuits to provide release of power to security system upon fire alarm$1,200
6750107-EL2020-02-13Electrical520 WESTLAKE AVE NElectrical system, complete (including lighting, lighting controls, distribution, branch power), for 12-story shell and core (322ksf) for future tenant office space + 4 levels of u$7,402,586
6771058-EL2020-02-11Electrical2200 7TH AVEOwner changes to relocate lighting and power circuitry on tower 2 levels 4, 5, & 6$41,000
6765643-EL2020-01-07Electrical810 3RD AVECentral Bldg Suite 324 & 330: Modifications to existing fire alarm system for tenant improvement.$7,000
6765626-EL2020-01-07Electrical810 3RD AVECentral Bldg Suite 730: modifications to existing fire alarm system for tenant improvement.$7,000

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Seattle permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →