Northwest Fire Systems appears on 50 Seattle permit records from 2023 through 2026, most often electrical (90% of the record).

Permit categories

CategoryPermitsShare
Electrical4590%
Fire protection510%

2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.

Activity by year

YearPermits issued
20231
20243
202538
20268

Busiest year on record: 2025, with 38 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
1204 MINOR AVE2026-08-11
1406 3RD AVE W2026-08-06
219 E GARFIELD ST2026-07-29
1516 15TH AVE W2026-02-26
1415 5TH AVE2026-02-11
211 LENORA ST2026-02-04
2203 E UNION ST2026-01-30
2980 SW AVALON WAY2026-01-12
4219 S OTHELLO ST2025-12-05
2970 SW AVALON WAY2025-11-17
805 MADISON ST2025-11-06
822 QUEEN ANNE AVE N2025-10-23
2210 E CHERRY ST2025-10-16
300 1ST AVE W2025-10-10

49 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $285,298, median $6,428. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

50 permits; open the full list
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
7157548-EL2026-08-11Electrical1204 MINOR AVEreplace FACP with firelite conventional FACP, add cell dialer.
7156997-EL2026-08-06Electrical1406 3RD AVE WRelocating 3 horn only devices.
7125694-EL2026-07-29Electrical219 E GARFIELD STReplacement of an existing fire alarm system. A new fire alarm control panel will be installed with initiating devices in the same location as the existing devices. The notificatio$30,412
7128678-EL2026-02-26Electrical1516 15TH AVE WUPGRADE OF A FIRE ALARM SYSTEM IN AN EXISTING NON-SPRINKLERED BUILDING. NEW FIRE ALARM PANEL IS BEING INSTALLED ALONG WITH NOTIFICATON DEVICES AS PER THE APPLICABLE CODES, WITH PUL$27,210
7128878-EL2026-02-11Electrical1415 5TH AVE
7127864-EL2026-02-04Electrical211 LENORA ST
7127322-EL2026-01-30Electrical2203 E UNION ST
7124487-EL2026-01-12Electrical2980 SW AVALON WAYProject description Installing a new Telguard cellular dialer to monitor the fire alarm control panel.
7119873-EL2025-12-05Electrical4219 S OTHELLO STTI project. Demo phase: remove and secure existing devices to reduce false alarms during construction. Recircuit and reinstall NAC. Installing three new strobes and one new horn st$6,386
7110970-EL2025-11-17Electrical2970 SW AVALON WAYReplacing existing system to get customer off of fire watch; then provide parts and programming for code upgrade.$26,795
7093920-EL2025-11-06Electrical805 MADISON STModifying the existing fire alarm system. Suite 410 notification circuit will be relocated throughout Suite 410. New LED speaker/strobes will be installed in Suite 410. The RPS is $6,500
7102620-EL2025-10-23Electrical822 QUEEN ANNE AVE NInstalling a new manual and automatic fire alarm system, including a new panel and notification devices in a four-story apartment builiding - 280 devices total.$59,522
7092779-EL2025-10-16Electrical2210 E CHERRY STInstalling a new fire alarm system with notification, elevator recall and pressurization controls, and sprinkler monitoring.$173,000
7111161-EL2025-10-10Electrical300 1ST AVE WInstalling a new cell dialer to monitor the FACP.$2,080
7102807-EL2025-09-11Electrical37 S HUDSON STNew manual and automatic fire alarm system. New fire alarm panel is being installed along with notification devices as per the applicable codes. Waterflow switch is being monitored$46,412
7105041-EL2025-09-04Electrical84 UNION STUpgrading the fire alarm panel monitoring from phone lines to cellular - installing Telguard cell device.$2,210
7104198-EL2025-08-28Electrical1330 BOREN AVEEmergency panel replacement$14,493
7077015-EL2025-08-22Electrical425 N 85TH STInstalling a new fire alarm control system. The fire alarm control panel will be monitored off-site through a new AES radio. Remote power supplies will be installed to provide powe$285,298
7100202-EL2025-08-06Electrical2320 W COMMODORE WAYInstalling a cell dialer to monitor the FACP.$2,210
7098575-EL2025-07-28Electrical601 AURORA AVE NInstalling a new cell dialer to monitor the FACP.$2,353
7082130-EL2025-07-28Electrical420 NE 72ND STModifying the existing fire alarm system. A monitor module will be installed to supervise for when the generator is running. A smoke detector will be installed in the generator mac$15,431
7098451-EL2025-07-25Electrical3701 S HUDSON STReplacing the existing fire alarm panel with a newer model fire alarm control panel. The FACP is located in the fire control room. All existing initiating and notification devices $8,400
7098318-EL2025-07-25Electrical2219 4TH AVEInstalling a cell dialer to monitor the FACP.$2,960
7098316-EL2025-07-25Electrical1915 2ND AVEInstalling cell dialer to monitor the FACP.$2,960
7097418-EL2025-07-21Electrical3701 S NORFOLK STInstalling a new cellular device to monitor the FACP.$2,840
7096100-EL2025-07-14Electrical224 1ST AVE NInstalling three new notification devices.$6,470
7096119-EL2025-07-14Electrical5555 14TH AVE NWAdding three alarm horn-strobe/strobes. [C.Kenefick 8/22/2025 - three additional fire alarm devices added to permit. Post admin fee waived.]$5,260
7089897-EL2025-07-10Electrical411 N 50TH STInstalling a new fire alarm system in a temporary classroom structure. The FACP will be located in the structure's office space. The AES radio will be installed to provide off-sit$17,700
7087673-EL2025-06-25Electrical1301 ALASKAN WAYMODIFYING THE EXITING FIRE ALARM SYSTEM. AN ADDITIONAL REMOTE ANNUNCIATOR WILL BE INSTALLED IN THE CONTROL ROOM FOR THE VR RIDE. A MANUAL PULL STATION WILL ALSO BE INSTALLED IN THE$8,135
7083901-EL2025-05-28Electrical401 ALASKAN WAY SInstalling a fire alarm control panel and notification. One dual monitor module will be installed to monitor the conventional fire alarm pull stations and smoke detectors for alarm$5,613
7084595-EL2025-05-28Electrical2711 NE 115TH STINSTALLATION OF A NEW MANUAL AND AUTOMATIC FIRE ALARM SYSTEM IN AN EXISTING NON SPRINKLERED BUILDING. NEW FIRE ALARM PANEL IS BEING INSTALLED ALONG WITH NOTIFICATON DEVICES AS PER $20,843
7087236-EL2025-05-21Electrical501 S JACKSON STInstalling Telguard cell dialer to monitor FACP.$2,850
7066936-FS2025-05-02Fire protection4035 STONE WAY NPROJECT ORIGINALLY STARTED UNDER PERMIT NUMBER 6815641-FS. WORK ENDED AND PERMIT EXPIRED. NORTHWEST FIRE SYSTEMS (NWFS) TO RE-START AND COMPLETE PROJECT WITH ONE WET PIPE AUTOMATIC$56,534
7082604-EL2025-04-25Electrical4719 15TH AVE NEReplacing booster power supply - HPF-PS6$3,075
7077990-EL2025-03-28Electrical2421 NW MARKET STInstalling an AES radio to monitor the FACP.$3,750
7074937-EL2025-03-12Electrical3701 S HUDSON STCellular Dialer Install and Monitoring Conversion$2,800
7073855-EL2025-03-05Electrical3230 16TH AVE WCellular monitoring conversion$2,840
7073163-EL2025-03-03Electrical1415 WESTERN AVEAdding 3 notification devices and 1 power supply.$9,850
7067268-EL2025-02-27Electrical4351 15TH AVE SNORTHWEST FIRE SYSTEMS WILL BE MODIFYING THE EXISTING FIRE ALARM SYSTEM. NOTIFICATION WILL BE INSTALLED THROUGHOUT THE SUITE 102 TO PROVIDE PROPER NOTIFICATION COVERAGE. CURRENT DR$7,938
7064945-EL2025-02-20Electrical3802 S OTHELLO STFire Alarm TI; relocating 3 devices and demoing 5 devices. Submitting plans to complete permit # 7058929-EL$3,110
7071133-EL2025-02-18Electrical12012 10TH PL NEInstalling a cellular monitoring device to monitor the FACP$2,450
7071110-EL2025-02-18Electrical12002 ROOSEVELT WAY NEInstalling a cellular monitoring device to monitor the FACP$2,450
7071054-EL2025-02-18Electrical522 N 85TH STInstalling Telguard cellular communicator.$2,450
7070594-EL2025-02-14Electrical910 JOHN STNorthwest Fire Systems is adding three speaker ceiling strobes and one ceiling strobe.$2,609
7066085-EL2025-02-10Electrical400 QUEEN ANNE AVE NNORTHWEST FIRE SYSTEMS WILL BE UPDATING THE EXISTING FIRE ALARM SYSTEM. ALL EXISTING NOTIFICATION AND DETECTION ON THE 1ST FLOOR WILL BE REPLACED. A MONITOR MODULE WILL BE INSTALLE$12,450
7064042-EL2025-01-31Electrical5201 GREEN LAKE WAY NWORKING WITH MASTERCRAFT ELECTRIC TO INSTALL A NEW FIRE ALARM SYSTEM FOR LOWER WOODLAND REHAB.$7,899
7055144-FS2024-12-06Fire protection706 N 59TH STProvide a new fire sprinkler system per NFPA 13D. Total of 33 sprinklers supplied by a stand alone pump and tank.$11,938
7033418-FS2024-09-30Fire protection353 N 137TH STProviding a new fire sprinkler system per NFPA 13D. Total of 10 sprinkler supplied by city water.$4,757
7022492-FS2024-06-03Fire protection6738 38TH AVE SWProvide a new fire sprinkler system per NFPA 13D. Total of 37 sprinkler supplied by city water.$9,593
7000812-FS2023-12-18Fire protection11314 SAND POINT WAY NEProviding a new Fire sprinkler per NFPA 13D. Total of 40 sprinklers supplied by a stand alone tank and pump.$0

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Seattle permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →