COMPANY RECORD · SEATTLE, WA
Northwest Electric & Solar — permit history in Seattle, WA
Northwest Electric & Solar appears on 2,439 Seattle permit records from 2015 through 2026, all of them electrical.
Permit categories
| Category | Permits | Share |
|---|---|---|
| Electrical | 2439 | 100% |
Activity by year
| Year | Permits issued |
|---|---|
| 2015 | 205 |
| 2016 | 255 |
| 2017 | 189 |
| 2018 | 242 |
| 2019 | 232 |
| 2020 | 211 |
| 2021 | 313 |
| 2022 | 238 |
| 2023 | 270 |
| 2024 | 226 |
| 2025 | 28 |
| 2026 | 30 |
Busiest year on record: 2021, with 313 permits. One project can account for several filings, so read this as filing activity rather than workload.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 323 NW 54TH ST | 2026-08-26 |
| 21 W COMSTOCK ST | 2026-08-17 |
| 3700 W COMMODORE WAY | 2026-08-14 |
| 1388 ALKI AVE SW | 2026-08-03 |
| 1711 MADRONA DR | 2026-07-29 |
| 615 W PROSPECT ST | 2026-07-28 |
| 3314 SW HINDS ST | 2026-07-15 |
| 363 NW 76TH ST | 2026-06-25 |
| 2735 NE 103RD ST | 2026-06-22 |
| 410 18TH AVE E | 2026-06-16 |
| 5238 39TH AVE NE | 2026-06-15 |
| 410 NE 70TH ST | 2026-06-15 |
| 1902 31ST AVE S | 2026-06-11 |
| 5822 56TH AVE NE | 2026-06-11 |
1,798 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $1,000,000, median $0. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Permits on record
2,439 permits; open the 50 most recent
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| 7159945-EL | 2026-08-26 | Electrical | 323 NW 54TH ST | Installing circuit for EV charger | |
| 7155044-EL | 2026-08-17 | Electrical | 21 W COMSTOCK ST | Inside electrical room install 50 breaker disconnect to unit 102. Inside disconnect install Tesla load shedding module. From disconnect surface mount 3/4 inch flexible conduit 5-8f | $2,000 |
| 7154809-EL | 2026-08-17 | Electrical | 21 W COMSTOCK ST | Pamela Kraus EVC installation: Inside electrical room install to unit # 501 a 50 amp breaker disconnect. Inside breaker disconnect install Tesla load shedding module. From disconne | $2,000 |
| 7155085-EL | 2026-08-17 | Electrical | 21 W COMSTOCK ST | Inside electrical room install 50 amp breaker disconnect to unit 301. Inside disconnect install Tesla load shedding module. From disconnect surface mount 3/4 inch flexible conduit | $2,000 |
| 7155060-EL | 2026-08-17 | Electrical | 21 W COMSTOCK ST | Inside electrical room install to unit 301 50 amp breaker disconnect. Inside breaker disconnect install Tesla load shedding module. From disconnect surface mount 3/4 inch flexible | $2,000 |
| 7158211-EL | 2026-08-14 | Electrical | 3700 W COMMODORE WAY | Install hardwired charger up to 35 ft from electrical panel. Inside sub panel install NWEs supplied Load shedding module. From Sub panel surface mount 3/4 inch EMT conduit 35ft ins | |
| 7156296-EL | 2026-08-03 | Electrical | 1388 ALKI AVE SW | Inside electrical room install DCC-12 to condo unit along with 50 amp breaker disconnect. From breaker disconnect surface mount 3/4 inch flex to nearest existing EV J box. Pull #6 | |
| 7155601-EL | 2026-07-29 | Electrical | 1711 MADRONA DR | Install hardwired charger up to 5 ft from electrical panel. From sub panel inside garage. Install NWES supplied Tesla load shedding module. From sub panel surface mount 3/4 inch fl | |
| 7155351-EL | 2026-07-28 | Electrical | 615 W PROSPECT ST | Max Bardon - EVC installation | |
| 7153205-EL | 2026-07-15 | Electrical | 3314 SW HINDS ST | From breaker panel surface mount 3/4 inch flexiblele conduit 5ft from breaker panel. Install customer supplied EV charger. Charger will be mounted in an attached garage. EV charger | |
| 7150099-EL | 2026-06-25 | Electrical | 363 NW 76TH ST | EVC installation | |
| 7149344-EL | 2026-06-22 | Electrical | 2735 NE 103RD ST | EVC installation | |
| 7148392-EL | 2026-06-16 | Electrical | 410 18TH AVE E | Install hardwired charger up to 5 ft from electrical panel. From sub panel in garage surface mount 3/4 inch flexible conduit within 5ft. Install customer supplied Tesla universal w | |
| 7148132-EL | 2026-06-15 | Electrical | 5238 39TH AVE NE | - Remove existing gear as needed so new siding can be installed. - Replace gear in existing location. - Add new 120v GFCI outlet outside for new awni | |
| 7148120-EL | 2026-06-15 | Electrical | 410 NE 70TH ST | Inside electrical room install Tesla load shedding module with 50 amp disconnect to unit #201. From disconnect use pre existing raceway into parking garage. From parking garage J b | |
| 7147745-EL | 2026-06-11 | Electrical | 1902 31ST AVE S | Matthew Hall - EVC installation | |
| 7147747-EL | 2026-06-11 | Electrical | 5822 56TH AVE NE | Install hardwired charger 5 ft from electrical panel. From pre wired J box install customer supplied EV charger. Remove 2 pole 50 amp GFCI breaker in sub panel. Charger will be mou | |
| 7147718-EL | 2026-06-11 | Electrical | 1305 E PROSPECT ST | EV charger From Tesla Gateway surface mount 3/4 inch EMT conduit 8-10ft. Install customer supplied EV charger. Commission EV charger on 2-pole 60 amp breaker. Inside Tesla Gateway | |
| 7134835-EL | 2026-03-24 | Electrical | 5509 5TH AVE NW | Ou Ye - EVC installation | |
| 7132681-EL | 2026-03-10 | Electrical | 6517 6TH AVE NW | From breaker panel surface mount 3/4 inch flexible conduit 30-35ft inside unfinished basement. Drill outside and transition into PVC conduit. Install 60 amp non fused disconnect ou | |
| 7131156-EL | 2026-02-26 | Electrical | 1250 ALKI AVE SW | - From EV charger house panel run _ inch flexible conduit into parking garage. - Inside parking garage transition into _ inch EMT conduit. - Use existing | |
| 7128672-EL | 2026-02-10 | Electrical | 5315 46TH AVE SW | ||
| 7128510-EL | 2026-02-09 | Electrical | 4057 SW HOLGATE ST | Customer is purchasing charger separately and will provide it at the time of the installation,- From sub panel inside the house run 4-3 romex cable 20ft under stairs. drill outsid | |
| 7127944-EL | 2026-02-04 | Electrical | 530 BROADWAY E | ||
| 7127762-EL | 2026-02-03 | Electrical | 9546 2ND AVE NW | ||
| 7127740-EL | 2026-02-03 | Electrical | 5315 46TH AVE SW | Remove existing overhead service. Move new 200amp meter/main overhead service to front SE part of House. From new meter/ main surface mount 2 inch PVC outside 20-25ft. LB | |
| 7126878-EL | 2026-01-28 | Electrical | 1564 ALKI AVE SW | In main electrical room install 200amp load shedding module to unit 404 with a 50amp breaker disconnect. From smart switch use existing EV raceway to closest J box in uppe | |
| 7126463-EL | 2026-01-26 | Electrical | 225 27TH AVE E | ||
| 7126398-EL | 2026-01-26 | Electrical | 2612 32ND AVE W | ||
| 7125512-EL | 2026-01-19 | Electrical | 3811 29TH AVE W | ||
| 7109609-EL | 2025-10-01 | Electrical | 4721 S ORCAS ST | Panel change - like for like - Randy Nelson 14433 | $0 |
| 7100937-EL | 2025-08-11 | Electrical | 1664 FEDERAL AVE E | 14351 Lisa Erlanger From Sq D QO breaker panel inside garage install load shedding module inside panel. - From Sub panel surface mount _ Inch EMT pipe 30-35ft from the panel. - Ei | $0 |
| 7095556-EL | 2025-07-10 | Electrical | 7100 55TH AVE S | This is for the remodel of a basement. Going from an unfinished basement to a finished basement with bedrooms a bathroom and an office and exercise room. | $40,000 |
| 7090351-EL | 2025-06-10 | Electrical | 4949 ERSKINE WAY SW | OH temp pole | $500 |
| 7089437-EL | 2025-06-04 | Electrical | 4828 NE 85TH ST | Remodel.; [7/1/26 RN Renewal/Reinstatement fee added] | $40,000 |
| 7088040-EL | 2025-05-28 | Electrical | 8343 32ND AVE NW | Kitchen remodel. | $20,297 |
| 7087841-EL | 2025-05-27 | Electrical | 1620 43RD AVE E | add fixture, like for like as well(C3) | $0 |
| 7087431-EL | 2025-05-22 | Electrical | 1125B 23RD AVE E | Child permit for DADU. | $400 |
| 7084220-EL | 2025-05-06 | Electrical | 625 HILLSIDE DR E | set up current permanent into temp for construction use | $0 |
| 7082753-EL | 2025-04-28 | Electrical | 99 UNION ST | Modification of lighting and outlet circuits. | $15,000 |
| 7079182-EL | 2025-04-04 | Electrical | 6052 52ND AVE S | EVC | $0 |
| 7075727-EL | 2025-03-26 | Electrical | 530 BROADWAY E | Inside electrical room install 100 amp smart switch to unit 510 with 30 amp breaker disconnect -Run 8-4 MC cable in pre existing EV raceway 280ft to parking spot #46. -At par | $3,425 |
| 7071672-EL | 2025-03-18 | Electrical | 1104 41ST AVE E | (6) Enphase 5P (2) Enphase system controllers Backing up both legs of service 24) Silfab 440 QD Prime NTC (24) Enphase IQ8M | $4,600 |
| 7075718-EL | 2025-03-17 | Electrical | 11015 28TH AVE NE | rebuild after tree strike. 3/19/25 r m, 7051053-el for SCL safety check and hot tub. | $0 |
| 7071669-EL | 2025-02-21 | Electrical | 1104 41ST AVE E | OTC Wall cover for future solar and ESS | $1,000 |
| 7069947-EL | 2025-02-11 | Electrical | 1956 EDGEMONT PL W | EVC - Geoff Derry | $0 |
| 7069743-EL | 2025-02-10 | Electrical | 3824 EVANSTON AVE N | 13744 Stonewater HOA Raceway - Inside electrical room core drill 4 -1 ¼ hole into parking garage. - Install 4-1 ¼ EMT conduits. - Install J boxes on each side of the wall. | $0 |
| 7069396-EL | 2025-02-07 | Electrical | 11923 LAKESIDE PL NE | EVC - Anne Schwabel | $0 |
| 7069338-EL | 2025-02-07 | Electrical | 2624 E OLIVE ST | EVC - Elie Ahovi | $0 |
| 7069246-EL | 2025-02-06 | Electrical | 1700 17TH AVE E | replace mast due to storm damage last week | $3,000 |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Source and limits
Public Seattle permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →