Northwest Electric And Solar appears on 176 Seattle permit records from 2023 through 2026, all of them electrical.

Permit categories

CategoryPermitsShare
Electrical176100%

Activity by year

YearPermits issued
202324
202416
2025104
202632

Busiest year on record: 2025, with 104 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
4514 BAGLEY AVE N2026-08-11
1902 31ST AVE S2026-08-11
3350 58TH AVE SW2026-07-08
818 36TH AVE2026-07-01
3037 64TH AVE SW2026-07-01
7212 DAYTON AVE N2026-06-04
1103 21ST AVE S2026-05-28
8834 2ND AVE S2026-05-08
1516 18TH AVE S2026-05-01
2342 41ST AVE E2026-04-11
2222 NOB HILL AVE N2026-04-07
4949 ERSKINE WAY SW2026-03-27
5959 CORSON AVE S2026-03-18
610 37TH AVE2026-03-11

133 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $1 to $70,000, median $4,371. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

176 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
7157572-EL2026-08-11Electrical4514 BAGLEY AVE NSPAN 40 Panel
7157550-EL2026-08-11Electrical4514 BAGLEY AVE N03) SILFAB SOLAR SIL-520 QM MODULES ( 01) TESLA POWERWALL3 WITH 11.5KW BUILT-IN INVERTER (01) TESLA POWERWALL 3 BATTERY (01) TESLA BACKUP GATEWAY 3
7157582-EL2026-08-11Electrical1902 31ST AVE SSPAN 40 Panel
7151027-EL2026-07-09Electrical1902 31ST AVE S12.76KW DC/ 10.12KW AC ROOF MOUNTED PV SYSTEM:(29) SILFAB SOLAR SIL-440 QD MODULES(29) ENPHASE IQ8AC-72-M-US (240V) MICROINVERTERS(01) ENPHASE IQ COMBINER 5/5C PANEL [7/9/2026 BGO$21,875
7151916-EL2026-07-08Electrical3350 58TH AVE SWsmall kitchen remodel
7150685-EL2026-07-06Electrical4514 BAGLEY AVE NInstallation of (3)Silfab 520-QM Solar panels, (2)Tesla Powerwall 3s, (1)Tesla BUG, (1)SPAN 40 Space Main Breaker Panel [7/6/26 BGO Separate OTC permit required for 200A SPAN panel$22,652
7149889-EL2026-07-01Electrical818 36TH AVEInstallation of (35) Silfab 440-QD Prime NTC, (1) Tesla Powerwall 3 Inverter, (1) Tesla Back Up Gateway [6/30/26 BGO - Approved PV+ESS Plan Set]$22,842
7151026-EL2026-07-01Electrical3037 64TH AVE SWAdding (8) JA JAM54D41 MB, (8) Enphase IQ8AC-M-US to an existing solar system
7146351-EL2026-06-04Electrical7212 DAYTON AVE N9.68KW DC/ 7.04 KW AC ROOF MOUNTED PV SYSTEM: (22) SILFAB SOLAR SIL-440 QD MODULES (22) ENPHASE IQ8MC-72-M-US (240V) MICROINVERTERS (01) ENPHASE IQ COMBINER 5/5C PANEL
7145285-EL2026-05-28Electrical1103 21ST AVE SInstallation of (1) EVC
7145044-EL2026-05-27Electrical818 36TH AVEAdding one feeder for future solar and battery installation.
7142245-EL2026-05-08Electrical8834 2ND AVE S(1) EVC Installation front of garage (outside) panel in Garage
7141106-EL2026-05-01Electrical1516 18TH AVE SEVC Installation outside of home, panel in laundry room.
7137880-EL2026-04-11Electrical2342 41ST AVE EBathroom remodel
7137224-EL2026-04-07Electrical2222 NOB HILL AVE NSpan Panel change
7135587-EL2026-03-27Electrical4949 ERSKINE WAY SW200A overhead temp pole
7134019-EL2026-03-18Electrical5959 CORSON AVE SAdding 10 locations of Cat6 2 runs to each location
7133028-EL2026-03-11Electrical610 37TH AVERemodel with 320 Amp service upgrade. [C.Kenefick 3/24/2026 - Service fee adjusted to reflect 320a service. Prior payment for 200a service applied.]
7132968-EL2026-03-11Electrical216 40TH AVE ENew feeder for dock and 30A circuit for pedestal
7130546-EL2026-02-23Electrical6854 51ST AVE NEKitchen/Bathroom remodel and Span panel install
7130284-EL2026-02-20Electrical5747 WOODLAWN AVE NInstallation of (1) EVC
7128184-EL2026-02-19Electrical625 HILLSIDE DR EInstallation of (2)Tesla PW3s, (1)Tesla DC Expansion, (1)Tesla Gateway 3 [2/19/26 BGO - Approved ESS portion of renewable energy system]$25,000
7129937-EL2026-02-18Electrical1817 12TH AVE WInstallation of (1)EVC
7128559-EL2026-02-09Electrical4949 ERSKINE WAY SWNew construction build
7126142-EL2026-02-03Electrical5767 S OAKLAWN PL(39)Silfab 440-QD Solar Panels, (2)Tesla PVIs [2/2/26 BGO - Approved PV Plan Set] [6/8/2026 BGO - Approved Revision to include existing meter with Emergency Disconnects]$19,200
7127187-EL2026-01-29Electrical2612 32ND AVE W
7127037-EL2026-01-29Electrical814 E BLAINE ST
7125896-EL2026-01-21Electrical3811 29TH AVE W
7124984-EL2026-01-14Electrical1936 38TH AVE E
7124724-EL2026-01-13Electrical3700 E UNION ST
7124071-EL2026-01-08Electrical1120 39TH AVE E[C.Kenefick 1/28/2026 - Two additional 50a circuits and one 100a feeder added to permit.]$1
7123974-EL2026-01-07Electrical10044C RAVENNA AVE NEEV charger to be powered by 50 amp Siemens breaker. UNIT C
7123072-EL2025-12-30Electrical1208 SHENANDOAH DR EBATTERIES ARE UNDER PERMIT 7117156-EL - WE JUST WANT THE BATTERIES FINALED SO THE HOMEOWNER CAN RECIEVE THE TAX CREDIT. 7117156-EL IS UNDER PLAN REVIEW BECAUSE WE ADDED FUEL CELLS$30,000
7122860-EL2025-12-29Electrical2009A DEXTER AVE NElectric vehicle charging station install$250
7120769-EL2025-12-23Electrical5450 37TH AVE SW(2) FRANKLINWH APOWER 2 BATTERY storage system added to existing solar [12/12/25 BGO - Fees adjusted for 30kWH Battery with Controller] [12/16/25 BGO - Approved ESS Add to Existing$19,200
7122397-EL2025-12-23Electrical5142 48TH AVE NE1 pre wired EVC and changing out 2 fixtures$220
7120833-EL2025-12-15Electrical9522 LAKE SHORE BLVD NE15.400KW DC/ 15.200KW AC ROOF MOUNTED PV SYSTEM [12/15/25 BGO - Approved PV Plan Set] (35) SILFAB SOLAR SIL-440 QD MODULES (02) TESLA SOLAR INVERTER 7.6 [240V] INVERTERS$19,200
7120848-EL2025-12-11Electrical12500 12TH AVE NW(1) EVC$250
7120648-EL2025-12-10Electrical12219 PHINNEY AVE NPanel upgrade (like for like)$3,000
7120612-EL2025-12-10Electrical12219 PHINNEY AVE NEVC$600
7117156-EL2025-12-05Electrical1208 SHENANDOAH DR EINSTALLATION OF TESLA GATEWAY 3 [12/4/25 BGO - Approved ESS Plan Set] [12/30/25 BGO - Approved Revision; Fuel Cell] 2X TESLA POWER$45,000
7119606-EL2025-12-04Electrical7338 9TH AVE NWBasement/upper floor remodel [C.Kenefick 5/20/2026 - 200a service added to permit.]$15,000
7119161-EL2025-12-02Electrical2009 12TH AVE Ecircuit extension and relocation$5,000
7118113-EL2025-11-24Electrical6733 9TH AVE NW1 EVC$1,800
7114002-EL2025-11-20Electrical3710 E BLAINE ST(2) Tesla PW3s (1) Tesla DC Expansion with Tesla Backup Gateway 3 [11/18/25 BGO - Approved ESS Add to PV Plan Set]$27,771
7116585-EL2025-11-13Electrical12500 12TH AVE NW(N) 10.120KW DC/ 7.600KW AC ROOF MOUNTED PV SYSTEM (23) SILFAB SOLAR SIL-440 QD MODULES (01) TESLA SOLAR INVERTER 7.6KW (240V) INVERTER (08) TESLA SOLAR SHUTDOWN DEVICE MCI-2$5,000
7116622-EL2025-11-13Electrical4949 ERSKINE WAY SWufer install$1,000
7116349-EL2025-11-12Electrical4117B WALLINGFORD AVE NInstallation of EVC$827
7116237-EL2025-11-11Electrical9611 39TH AVE SWEV charger to be powered by 60 amp Eaton BR breaker$1,379
7115775-EL2025-11-07Electrical2223 WAVERLY WAY Efixture additions$6,000

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Seattle permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →