Resound Energy LLC appears on 163 Bellevue permit records from 2015 through 2026, most often electrical (99.4% of the record).
Permit categories
| Category | Permits | Share |
|---|---|---|
| Electrical | 162 | 99.4% |
| General construction | 1 | 0.61% |
2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.
Activity by year
| Year | Permits issued |
|---|---|
| 2015 | 6 |
| 2016 | 5 |
| 2017 | 1 |
| 2018 | 2 |
| 2019 | 10 |
| 2020 | 13 |
| 2021 | 45 |
| 2022 | 17 |
| 2023 | 22 |
| 2024 | 23 |
| 2025 | 15 |
| 2026 | 4 |
Busiest year on record: 2021, with 45 permits. One project can account for several filings, so read this as filing activity rather than workload.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 177 107th Ave NE | 2026-09-15 |
| 2606 116th Ave NE | 2026-09-08 |
| 11030 Main St - Unit site | 2026-06-15 |
| 10333 Main St | 2026-05-12 |
| 10701 Main St | 2025-11-21 |
| 10710 NE 10th St | 2025-10-23 |
| 14111 SE 6th St - Bldg CLUB | 2025-10-17 |
| 10050 NE 10th St - Unit site | 2025-10-06 |
| 2030 155th Pl NE | 2025-08-26 |
| 188 Bellevue Way NE - Unit 1001 | 2025-07-30 |
| 11130 NE 10th St | 2025-07-30 |
| 1328 130th Ave NE | 2025-07-23 |
| 11405 NE 2nd Pl | 2025-07-11 |
| 1020 108th Ave NE | 2025-07-09 |
121 distinct addresses on record; the 14 most recent are shown. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Also named on permits at the same addresses
| Company | Shared addresses | Years |
|---|---|---|
| Innovative Systems Tech Inc | 24 | 2015–2026 |
| Adt LLC | 14 | 2015–2025 |
| Titan Electric Inc | 14 | 2015–2026 |
| Guardian Security Systems Inc | 13 | 2015–2026 |
| Unity Electric LP | 10 | 2015–2026 |
| Cochran Inc | 9 | 2015–2026 |
| Zorko Electric Inc | 9 | 2015–2026 |
| T C I Inc Paul Douglas Talbott | 9 | 2015–2026 |
Companies that also appear in Bellevue permit records at addresses where Resound Energy LLC filed, in any year. Sharing an address is a documented co-appearance, not proof that they worked on the same project or with each other.
Permits on record
163 permits; open the 50 most recent
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| 26 121462 BF | 2026-09-15 | Electrical | 177 107th Ave NE | A Multifamily Residential Alteration to Existing Structure Electrical Project Involving (1 Vehicle Charging Station, 1 Added or Altered Branch Circuits) | |
| 26 121128 BF | 2026-09-08 | Electrical | 2606 116th Ave NE | A Nonresidential Repair or Replacement Electrical Project Involving (26 Light Fixtures) | |
| 26 114164 BF | 2026-06-15 | Electrical | 11030 Main St - Unit site | A Multifamily Residential Alteration to Existing Structure Electrical Project Involving (6 Light Fixtures) | |
| 26 111342 BF | 2026-05-12 | Electrical | 10333 Main St | A Multifamily Residential Repair or Replacement Electrical Project Involving (10 Light Fixtures) | |
| 25 124872 BG | 2025-11-21 | Electrical | 10701 Main St | Installation of new 225A panel to feed (15) new EVSE | |
| 25 113785 BG | 2025-10-23 | Electrical | 10710 NE 10th St | Installing (1) New 112.5 KVA transformer fed from a 3p175a breaker, and (1) new 400amp panel. Installing (20) EV Chargers on (10) Dedicated circuits. | |
| 25 120850 BG | 2025-10-17 | Electrical | 14111 SE 6th St - Bldg CLUB | Scope is to remove (2) DualPort ChargePoint CT4000 EVSE & install (9) Wallbox EVSE fed from existing 200A outdoor cabana panel. | |
| 24 126977 BG | 2025-10-06 | Electrical | 10050 NE 10th St - Unit site | We are installing (1) New 400amp feeder and panel, installing (20) EV chargers off of the new panel | |
| 25 113217 BG | 2025-08-26 | Electrical | 2030 155th Pl NE | Installing (20) Wallbox Electric Vehicle Charging stations. Chargers to be fed from a new 225A panel which will be fed from existing house switchgear. Also installing SWTCH netwo | |
| 25 118523 BF | 2025-07-30 | Electrical | 188 Bellevue Way NE - Unit 1001 | A Multifamily Residential New Structure Electrical Project Involving (51 Vehicle Charging Station) | |
| 25 118524 BF | 2025-07-30 | Electrical | 11130 NE 10th St | A Multifamily Residential New Structure Electrical Project Involving (20 Vehicle Charging Station) | |
| 25 114896 BG | 2025-07-23 | Electrical | 1328 130th Ave NE | 11 EV chargers installed in parking garage Conduit and breakers are existing | |
| 25 116576 BF | 2025-07-11 | Electrical | 11405 NE 2nd Pl | A Multifamily Residential Repair or Replacement Electrical Project Involving (4 Vehicle Charging Station) | |
| 25 113986 BG | 2025-07-09 | Electrical | 1020 108th Ave NE | Reorganize breakers in panels H, H1, and H2 for physical real estate. Install 16 Xeal EV charging stations in stalls 259-262, 359-362, and 459-462. Rip and Replace CT4000s in stal | |
| 25 115028 BF | 2025-06-20 | Electrical | 10232 NE 10th St | A Multifamily Residential Alteration to Existing Structure Electrical Project Involving (1 Vehicle Charging Station) | |
| 25 108951 BG | 2025-06-03 | Electrical | 188 Bellevue Way NE - Unit 904 | Installing (4) New panels with (3) feed through sub panels. Removing existing ChargePoint EV chargers and installing (26) Tesla chargers., EV-1225.8 | |
| 25 111971 BF | 2025-05-28 | Electrical | 14640 NE 24th St | A Nonresidential Repair or Replacement Electrical Project Involving (400 Light Fixtures) | |
| 24 127008 BG | 2025-04-11 | Electrical | 900 108th Ave NE - Unit site | This scope is to install a total of (4) Electric Vehicle evercharge chargers in parking stalls right outside of electrical room. Power will be sourced from new 200A meter and panel | |
| 25 100222 BF | 2025-01-07 | Electrical | 13212 SE Eastgate Way | A Nonresidential Alteration to Existing Structure Electrical Project Involving (50 Light Fixtures) | |
| 24 129514 BF | 2024-12-17 | Electrical | 14205 SE 36th St | A Nonresidential Repair or Replacement Electrical Project Involving (400 Light Fixtures, 5 Added or Altered Branch Circuits) | |
| 24 127468 BF | 2024-12-02 | Electrical | 1100 112th Ave NE | A Multifamily Residential Repair or Replacement Electrical Project Involving (4 Added or Altered Branch Circuits) | |
| 24 123440 BF | 2024-10-07 | Electrical | 10232 NE 10th St | A Multifamily Residential Addition to Existing Structure Electrical Project Involving (1 Vehicle Charging Station) | |
| 24 122813 BF | 2024-09-24 | Electrical | 10232 NE 10th St | A Multifamily Residential Addition to Existing Structure Electrical Project Involving (1 Vehicle Charging Station) | |
| 24 113537 BG | 2024-08-26 | Electrical | 1100 112th Ave NE | Provide and install four (4) 40A branch circuits. Provide and install four (4) Electric Vehicle (EV) charging stations. | |
| 24 113566 BF | 2024-06-18 | Electrical | 915 118th Ave SE | A Nonresidential Repair or Replacement Electrical Project Involving (3 Light Fixtures) | |
| 24 113141 BF | 2024-06-10 | Electrical | 3605 132nd Ave SE | A Nonresidential Repair or Replacement Electrical Project Involving (70 Light Fixtures) | |
| 24 106704 BF | 2024-04-11 | Electrical | 688 110th Ave NE - Bldg 4 | A Nonresidential Alteration to Existing Structure Electrical | |
| 24 105105 BG | 2024-04-05 | Electrical | 103 Bellevue Way NE | Provide and install a total of sixteen (16) Evercharge chargers in P2 level of parking garage. Provide and install eight (8) 40A branch circuits. | |
| 24 105078 BG | 2024-03-26 | Electrical | 14700 NE 35th St | Provide and install four (4) Electric Vehicle (EV) charging stations. Provide and install four (4) 40A branch circuits. | |
| 24 103171 BG | 2024-03-14 | Electrical | 2700 156th Ave NE | Provide and install four (4) level 2 EV chargers on 60A circuits with 2 chargers power sharing on each circuit. | |
| 24 105112 BF | 2024-03-14 | Electrical | 333 108th Ave NE | A Nonresidential Alteration to Existing Structure Project Installing {262-Light Fixtures} Adding motion sensors to existing fixtures. | |
| 24 102211 BG | 2024-02-28 | Electrical | 14111 SE 6th St - Bldg CLUB | Provide and install four (4) Electrical Vehicle (EV) charging stations. Provide and install four (4) 40A branch circuits. | |
| 24 102099 BF | 2024-01-30 | Electrical | 14700 NE 35th St | A Multifamily Residential New Structure Electrical Project Involving (4 Vehicle Charging Station) | |
| 24 101036 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101037 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101034 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101033 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101035 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101039 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101041 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101038 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 24 101040 BF | 2024-01-05 | Electrical | 2501 148th Ave SE | A Multifamily Residential Alteration to Existing Structure Electrical | |
| 23 127693 BF | 2023-12-04 | Electrical | 320 108th Ave NE | A Multifamily Residential Repair or Replacement Electrical Project Involving (1 Vehicle Charging Station) | |
| 23 124291 BF | 2023-10-30 | Electrical | 10055 Meydenbauer Way SE - Unit 6 | A Multifamily Residential Alteration to Existing Structure Electrical Project Involving (1 Vehicle Charging Station, 1 Added or Altered Branch Circuits) | |
| 23 123223 BF | 2023-10-05 | Electrical | 688 110th Ave NE - Bldg 4 | A Nonresidential Repair or Replacement Electrical Project Involving (8 Added or Altered Branch Circuits), N/A | |
| 23 122984 BF | 2023-09-29 | Electrical | 10333 Main St | A Multifamily Residential Repair or Replacement Electrical Project Involving (250 Light Fixtures) | |
| 23 118686 BF | 2023-09-05 | Electrical | 14629 NE 37th Pl | A Multifamily Residential New Structure Electrical Project Involving (2 Vehicle Charging Station) | |
| 23 117816 BF | 2023-08-15 | Electrical | 3245 146th Pl SE | A Nonresidential Alteration to Existing Structure Project Installing {30-Light Fixtures} | |
| 23 117618 BF | 2023-08-11 | Electrical | 938 110th Ave NE | A Multifamily Residential Addition to Existing Structure Electrical Project Involving (6 Vehicle Charging Station, 3 Added or Altered Branch Circuits) | |
| 23 117604 BF | 2023-08-11 | Electrical | 10047 Main St | A Multifamily Residential Addition to Existing Structure Electrical Project Involving (1 Vehicle Charging Station, 1 Added or Altered Branch Circuits) |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Search these records
The 163 permits above are a static record through 2026. Select a year above to open that year’s records, or search Resound Energy LLC in Bellevue, WA by address, trade or date range.
Source and limits
Public Bellevue permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →
Is this your company? Show this public permit record on your website with a free badge.