Geauga Mechanical Company — permit history in Cleveland, OH

Geauga Mechanical Company appears on 450 Cleveland permit records from 2015 through 2026, most often mechanical / hvac (99.8% of the record).

Permit categories

CategoryPermitsShare
Mechanical / HVAC44999.8%
General construction10.22%

2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.

Activity by year

YearPermits issued
201523
201618
2017226
201893
201917
20204
202118
202211
20238
202412
202516
20264

Busiest year on record: 2017, with 226 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
200 PUBLIC SQ, CLEVELAND, OH, 441142026-07-09
1313 W 6TH ST, CLEVELAND, OH, 441132026-07-01
650 HURON RD, CLEVELAND, OH, 441152026-04-02
1027 SUPERIOR AVE, CLEVELAND, OH, 441142026-03-25
6701 CARNEGIE AVE, CLEVELAND, OH, 441242025-11-20
1 WADE OVAL DR, CLEVELAND, OH, 441062025-11-17
11328 EUCLID AVE, CLEVELAND, OH, 441062025-10-24
2074 ADELBERT RD AKA 2076, CLEVELAND, OH, 441062025-10-17
12018 MAYFIELD RD, CLEVELAND, OH, 441062025-10-02
2109 ADELBERT RD, CLEVELAND, OH, 441062025-09-17
2210 CIRCLE DR, CLEVELAND, OH, 441062025-08-19
2915 DETROIT AVE, CLEVELAND, OH, 441132025-07-25
6700 EUCLID AVE, CLEVELAND, OH, 441032025-07-24
5300 POSTAL RD, CLEVELAND, OH, 441352025-07-16

401 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $6,700,000, median $5,600. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

450 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
BCH26-0267622026-07-09Mechanical / HVAC200 PUBLIC SQ, CLEVELAND, OH, 44114INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EHX.AIR-$2,249.39, VAV'S-$4,340.00, 1 REFRIGERATION SYSTEM 25 TONS OR LESS BUILDING PERMIT NO BCB26-016551$89,761
BCH26-0268922026-07-01Mechanical / HVAC1313 W 6TH ST, CLEVELAND, OH, 44113INSTALL 3 HEAT PUMP, 1 DUCT HEATER, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH.AIR-$22,429.39, 7 REFRIGERATION SYSTEMS 25 TONS OR LESS ***BUILDING PERMIT NO B25028539***$89,761
H250083092026-04-02Mechanical / HVAC650 HURON RD, CLEVELAND, OH, 44115INSTALL 4 mechanical ventilation exhaust fans - $47,400 & NO2 / CO gas detection system.$259,400
BCH26-0053242026-03-25Mechanical / HVAC1027 SUPERIOR AVE, CLEVELAND, OH, 44114INSTALL 34 HEAT PUMPS, 10 DUCK HEATERS, 4 ROOFTOP HEATING/COOLING UNITS COST OF DUCK WORK 49000 ***BUILDING PERMIT NO B25031565***$2,000,000
H250377362025-11-20Mechanical / HVAC6701 CARNEGIE AVE, CLEVELAND, OH, 44124INSTALL 1 HEAT PUMP$2,000
H250377202025-11-17Mechanical / HVAC1 WADE OVAL DR, CLEVELAND, OH, 441064 AIR HANDLER, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $56,000. BUILDING PERMIT NO. B25011821.$1,800,000
H250351452025-10-24Mechanical / HVAC11328 EUCLID AVE, CLEVELAND, OH, 441062 BOILER. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $1237.95. BUILDING PERMIT NO. B25006693.$289,401
H250343242025-10-17Mechanical / HVAC2074 ADELBERT RD AKA 2076, CLEVELAND, OH, 44106INSTALL 1 SNOW MELT AKA: 2076 ADELBERT$115,685
H250261662025-10-02Mechanical / HVAC12018 MAYFIELD RD, CLEVELAND, OH, 44106INSTALL 1 ROOFTOP HEATING/COOLING UNIT, INSTALLED COST OF DUCTWORK SUPPLY/ RETURN / EXH. AIR - $6,656.98, KITCHEN HOOD EXHAUST DUCT SYSTEM COST - $8,612.46 BUILDING PERMIT NO B250$59,454
H250308112025-09-17Mechanical / HVAC2109 ADELBERT RD, CLEVELAND, OH, 441061 ROOFTOP HTG/COOLING UNIT, 1 HUMIDIFIER; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $15000. BUILDING PERMIT NO. B25005206.$235,000
H250274262025-08-19Mechanical / HVAC2210 CIRCLE DR, CLEVELAND, OH, 44106INSTALL 16 DUCT HTRS, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH.AIR $562,000 **** B25008324 ****$1,900,534
H250246992025-07-25Mechanical / HVAC2915 DETROIT AVE, CLEVELAND, OH, 44113INSTALLATION OFTHE FOLLOWING: 1 ROOFTOP HTG/ COOLING UNIT 200 LIN. FT. FUEL GAS PIPING INSTALLED COST OF DUCTWORK SUPPLY/RETURN/ EXH AIR: $19,000$164,129
H250242212025-07-24Mechanical / HVAC6700 EUCLID AVE, CLEVELAND, OH, 44103INSTALL 3 HEAT PUMPS, 3 ROOFTOP HEATING/COOLING UNITS, INSTALLED COST OF DUCTWORK SUPPLY/ RETURN/EXH. AIR - $12,000 BUILDING PERMIT NO B24018370$960,000
H250232112025-07-16Mechanical / HVAC5300 POSTAL RD, CLEVELAND, OH, 44135INSTALL 1 FURNACE, 3 WALL HEATERS, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR. - $3,000$174,000
H250211312025-07-09Mechanical / HVAC10510 BUCKEYE RD, CLEVELAND, OH, 44104INSTALLATION OF 1 WALL HEATER INSTALLATION OF 1 BLOWER COIL AND CONDENSING UNIT **********B25010669************$174,291
H250211512025-07-09Mechanical / HVAC2900 MARTIN LUTHER KING JR DR, CLEVELAND, OH, 44104INSTALLATION OF 2 ROOFTOP HTG/ COOLING UNIT(S). INSTALLED COST OF DUCTWORK SUPPLY / RETURN / EXH. AIR- $19,925 1 KITCHEN HOOD EXHAUST DUCT SYSTEM COST $19,186 **************B250$174,291
H250124862025-04-17Mechanical / HVAC18485 LAKE SHORE BLVD, CLEVELAND, OH, 441191 DUCT HTR, 2 ROOFTOP HTG/COOLING UNIT. 8 WALL HEATER, 84 HEAT PUMP, 1 SPACE HTR; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $281,000; 1 KITCHEN HOOD EXHAUST DUCT SYSTEM COS$1,538,500
H250111332025-04-07Mechanical / HVAC1200 W 76 ST, CLEVELAND, OH, 4410220813 ROOFTOP HTG/COOLING UNIT; 138 HEAT PUMP; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $36,000. BUILDING PERMIT NO. B23009991.$2,000,000
H250073112025-03-07Mechanical / HVAC1422 EUCLID AVE, CLEVELAND, OH, 44115INSTALL 31 HEAT PUMPS, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR - $215,000 BUILDING PERMIT NO B24006243- 13TH FLOOR$215,000
H240357472025-02-26Mechanical / HVAC10730 EUCLID AVE, CLEVELAND, OH, 441061 HEAT PUMP. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $4322. BUILDING PERMIT NO. B24026904.$20,047
H240301282024-10-25Mechanical / HVAC1 WADE OVAL, CLEVELAND, OH, 44106INSTALL (1) Air Handler BUILDING PERMIT: B24004127$60,000
H240284352024-10-08Mechanical / HVAC11150 EAST BOULEVARD, CLEVELAND, OH, 44106INSTALL 39 LINEARS DISTRIBUTORS FOR AIR ***************B24006670************$60,000
H240266872024-09-25Mechanical / HVAC11021 EAST BLVD, CLEVELAND, OH, 441063 ROOFTOP HTG/COOLING UNIT. 4 HEAT PUMP. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/ EXH AIR $260,000. BUILDING PERMIT NO. B24002268.$1,000,000
H240250922024-09-05Mechanical / HVAC2101 MARTIN LUTHER KING JR DR, CLEVELAND, OH, 44106Snowmelt- $30,000 BUILDING PERMIT NO B23015575$30,000
H240216932024-08-05Mechanical / HVAC2109 ADELBERT RD, CLEVELAND, OH, 44106INSTLAL 18 DUCT HTRS, 3 WALL HTRS, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR. $98,000. 3 REFRIGERATION SYSTEMS UNDER 25 TONS ***** B24004866 ****$733,000
H240186872024-07-09Mechanical / HVAC18491 LAKESHORE BLVD, CLEVELAND, OH, 4411985 REFRIGERATION SYSTEM TYPE R410A CAPACITY 196 TONS.$894,000
H240134712024-05-13Mechanical / HVAC2012 W 25TH ST, CLEVELAND, OH, 44113INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR ($2,400) BUILDING PERMIT: B24006064$60,000
H240119872024-04-23Mechanical / HVAC1 WADE OVAL DR, CLEVELAND, OH, 44106INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH.AIR $60,000. 6 VAV'S $5,000. **** B24004127 ****$643,000
H240082842024-03-19Mechanical / HVAC11310 WADE PARK AVE, CLEVELAND, OH, 441062 FURNACE, 2 HEAT PUMP; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $38,450. BUILDING PERMIT NO. B23025550. COMMUNITY CENTER$100,000
H240043922024-02-28Mechanical / HVAC2101 MARTIN LUTHER KING JR DR, CLEVELAND, OH, 441064 LEVELS HW EQUIPMENT. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $143,931. FIRE DAMPERS, VAV BOXES, DUCT SILENCERS $47,794. BUILDING PERMIT NO. B23015575.$845,000
H240054082024-02-27Mechanical / HVAC1501 EUCLID AVE, CLEVELAND, OH, 441141 ROOFTOP HTG/COOLING UNIT, 87 HEAT PUMP; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $200,000. REFRIGERATION SYSTEM TYPE R410A CAPACITY 120 TONS. BUILDING PERMIT NO. B2301234$1,200,000
H240054052024-02-27Mechanical / HVAC408 W ST CLAIR AVE, CLEVELAND, OH, 441137 HEAT PUMP; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $5000. REFRIGERATION SYSTEM TYPE 410A CAPACITY 10 TONS. BUILDING PERMIT NO. B23018575.$60,000
H230313212023-11-30Mechanical / HVAC3615 EUCLID AVE, CLEVELAND, OH, 441158 ROOFTOP HTG/COOLING UNIT, 40 WALL HTR, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $250,000. 1 REFRIGERATION SYSTEM TYPE 410A CAPACITY 34 TONS. BUILDING PERMIT NO. B22013653$2,000,000
H230252052023-09-22Mechanical / HVAC11001 CEDAR AVE, CLEVELAND, OH, 44106INSTALL 1 BOILER, SNOW MELT COST $20,000$63,200
H230223512023-08-24Mechanical / HVAC10969 CEDAR AVE, CLEVELAND, OH, 441062 HEAT PUMP, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $3000. BUILDING PERMIT NO. B23002364.$35,228
H230172902023-07-05Mechanical / HVAC1317 EUCLID AVE, CLEVELAND, OH, 44114INSTALL (1) 2 TON DUCTLESS MINI SPLIT INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR - $110,000 BUILDING PERMIT NO B23009006$185,000
H230161722023-06-21Mechanical / HVAC1050 E 9TH ST, CLEVELAND, OH, 44108KITCHEN HOOD EXHAUST DUCT SYSTEM COST - $40,000 BUILDING PERMIT NO. B23009733$50,000
H230115962023-05-03Mechanical / HVAC10900 CARNEGIE AVE 3, CLEVELAND, OH, 44106INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH.AIR $7,274.00.$7,274
H230059182023-03-06Mechanical / HVAC2140 SUPERIOR AVE, CLEVELAND, OH, 44114INSTALL 1 ROOFTOP HTG/COOLING UNIT. 1 KITCHEN HOOD EXHAUST DUCT SYSTEM COST. $50,000.$50,000
H230032552023-02-03Mechanical / HVAC6601 EUCLID AVE, CLEVELAND, OH, 44103INSTALL 3 FLOOR RADIANT FINNED TUBES BUILDING PERMIT NO. B20031713$60,000
H220307752022-11-21Mechanical / HVAC2140 SUPERIOR AVE, CLEVELAND, OH, 44114INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR - $4,500 BLACK IRON WELDED DUCT BUILDING PERMIT NO. B22015130$9,000
H220305772022-11-17Mechanical / HVAC4115 BRIDGE AVE, CLEVELAND, OH, 441134 ROOFTOP HTG/COOLING UNIT, 22 WALL HTR; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $18431. BUILDING PERMIT NO. B22005540.$714,977
H220267972022-10-07Mechanical / HVAC2210 CIRCLE DR, CLEVELAND, OH, 44106INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH.AIR $258,242.00 , VAV BOXES (39) AIR VALVES (27) COST $42372.00 ***** BUILDING PERMIT NO. B22001740 ****$937,793
H220213022022-08-11Mechanical / HVAC10300 CEDAR AVE, CLEVELAND, OH, 441142 ROOFTOP HTG/COOLING UNIT; 16 WALL HTR, 199 HEAT PUMP; INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $410,000. BUILDING PERMIT NO. B22007441.$1,800,000
H220185362022-07-14Mechanical / HVAC2074 ADELBERT RD, CLEVELAND, OH, 44106INSTALL 3 DUCT HEATERS, INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR - $69,240 BUILDING PERMIT NO. B22012354$180,606
H220165222022-06-23Mechanical / HVAC1940 E 6TH ST, CLEVELAND, OH, 441141 HEAT PUMP, INSTALLED COST OF DUCTWORK SUPPLY/ RETURN/EXH.AIR $2,000. ******* BUILDING PERMIT NO. B22002519 *******$9,275
H220165252022-06-23Mechanical / HVAC5506 DETROIT AVE, CLEVELAND, OH, 441022 BOILERS, 26 WALL HEATERS, 130 HEAT PUMPS, 4 SPACE HEATERS. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH. AIR $360,826. ***** BUILDING PERMIT NO. B21034093 ********$1,600,000
H220165182022-06-23Mechanical / HVAC2500 METRO HEALTH DR, CLEVELAND, OH, 441092 WALL HTRS, 6 HEAT PUMPS. ***** BUILDING PERMIT NO. B21032763 *******$45,000
H220104172022-04-21Mechanical / HVAC1300 E 9TH ST, CLEVELAND, OH, 441148 HEAT PUMPS. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH.AIR $10,000. ***** B21032106 *******$25,000
H220090842022-04-07Mechanical / HVAC1600 EUCLID AVE, CLEVELAND, OH, 441141 HEAT PUMP. INSTALLED COST OF DUCTWORK SUPPLY/RETURN/EXH AIR $4915. EXHAUST FAN. REFRIGERATION SYSTEM TYPE HP CAPACITY 2.5 TONS. WATER SOURCE HEAT PUMP CONNECTED TO BUILDING LOOP$14,000

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Cleveland permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →