COMPANY RECORD · RALEIGH, NC
Diamond Contracting, Inc. — permit history in Raleigh, NC
Diamond Contracting, Inc. appears on 87 Raleigh permit records from 2015 through 2026, all of them general construction.
Permit categories
| Category | Permits | Share |
|---|---|---|
| General construction | 87 | 100% |
Activity by year
| Year | Permits issued |
|---|---|
| 2015 | 16 |
| 2016 | 11 |
| 2017 | 12 |
| 2018 | 14 |
| 2019 | 9 |
| 2020 | 8 |
| 2021 | 2 |
| 2022 | 4 |
| 2023 | 4 |
| 2024 | 2 |
| 2025 | 2 |
| 2026 | 3 |
Busiest year on record: 2015, with 16 permits. One project can account for several filings, so read this as filing activity rather than workload.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 3920 Capital Hills Dr | 2026-03-25 |
| 3940 Capital Hills Dr | 2026-02-04 |
| 3201 Edwards Mill Rd 141 | 2026-01-21 |
| 1200 E Millbrook Rd STE 215 | 2025-11-17 |
| 2100 Glascock St | 2025-02-28 |
| 950 Peterson St | 2024-12-03 |
| 8005 Capital Blvd | 2024-10-25 |
| 3001 Edwards Mill Rd | 2023-08-14 |
| 4002 Capital Hills Dr | 2023-03-02 |
| 4000 Capital Hills Dr | 2023-02-23 |
| 7336 Creedmoor Rd | 2022-08-24 |
| 2526 Hillsborough St STE 200 | 2022-06-23 |
| 3201 Edwards Mill Rd STE 141 | 2022-01-27 |
| 8801 Durant Rd | 2021-04-26 |
54 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $6,563,250, median $113,692. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Permits on record
87 permits; open the 50 most recent
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| BLDNR-057771-2025 | 2026-03-25 | General construction | 3920 Capital Hills Dr | CONSTRUCTION AND INSTALLATION OF TEMPORARY TRAILERS FOR BUISNESS USE WHILE SHOWROOM RENOVATION IS GO | $879,988 |
| BLDNR-053619-2025 | 2026-02-04 | General construction | 3940 Capital Hills Dr | Renovation of vehicle showroom. new front exterior wall and glazing. Interior wall reconfiguration w | $2,734,301 |
| BLDNR-049817-2025 | 2026-01-21 | General construction | 3201 Edwards Mill Rd 141 | Selective interior demolition, new walls and finishes, plumbing, HVAC, electrical, fire alarm and sp | $172,149 |
| BLDNR-040791-2025 | 2025-11-17 | General construction | 1200 E Millbrook Rd STE 215 | First time interior fit up for Suite B205 for Salon Suites. Work includes new interior walls, mechan | $540,392 |
| BLDNR-052460-2024 | 2025-02-28 | General construction | 2100 Glascock St | ***Fire Station #7***Selective Interior demolition with limited new walls: new windows all over, new | $492,408 |
| BLDNR-012320-2024 | 2024-12-03 | General construction | 950 Peterson St | Replacing the existing wet sprinkler piping with a new dry pipe system. Replacing existing dry spri | $131,552 |
| BLDNR-048500-2024 | 2024-10-25 | General construction | 8005 Capital Blvd | LEITH TOYOTA 2194 SF RENOVATION OF EXISTING INTERIOR SPACES: SHOWROOM RESTROOMS, CUSTOMER LOUNGE, B | $240,397 |
| BLDNR-036027-2023 | 2023-08-14 | General construction | 3001 Edwards Mill Rd | Alteration of office space 1340SF 2-B CONST B OCC | $135,836 |
| BLDNR-063522-2022 | 2023-03-02 | General construction | 4002 Capital Hills Dr | INSTALLATION OF TEMPORARY Modular Office TRAILERS FOR BUISNESS USE WHILE SHOWROOM RENOVATION IS GOIN | $293,365 |
| BLDNR-001861-2023 | 2023-02-23 | General construction | 4000 Capital Hills Dr | Leith Audi- Reconfigure interior & install new interior finishes, lighting, ceiling materials 9865 S | $884,989 |
| BLDNR-061930-2022 | 2023-02-08 | General construction | 4000 Capital Hills Dr | Alteration Level 2, reconfiguration of space, removing 2 internal wash bays with the service area of | $39,338 |
| BLDNR-029076-2022 | 2022-10-12 | General construction | 4000 Capital Hills Dr | Addition of 3 detail bays attached to the existing service area of the buildings. new building addit | $140,812 |
| BLDNR-028787-2022 | 2022-08-24 | General construction | 7336 Creedmoor Rd | EXPANSION INTO SUITES 7334 AND 7340 FROM SUITES 7336 AND REMOVE TWO RESTROOMS. WALL DEMO. CHANGE OUT | $405,864 |
| BLDNR-022475-2022 | 2022-06-23 | General construction | 2526 Hillsborough St STE 200 | INTERIOR ALTERATION: 3-B CONST 1,868 SF OF SECOND FLOOR OFFICE BUSINESS OCCUPANCY SPACE SUITE TO IN | $147,310 |
| BLDNR-000125-2022 | 2022-01-27 | General construction | 3201 Edwards Mill Rd STE 141 | EUROPEAN WAX CENTER - FIT UP FOR TENANT2- B COSNT B OCC 1510 SF | $119,079 |
| BLDNR-003897-2021 | 2021-04-26 | General construction | 8801 Durant Rd | INSTALL 33 LIGHT POLE BASES AND ELECTRICA CONDUITS FOR INSTALLATION OF FUTURE PARKING LOT LIGHT POLE | $0 |
| BLDNR-049800-2020 | 2021-03-12 | General construction | 8801 Durant Rd | NEW BLDG - LEITH ADMINISTRATIVE BUILDING. SPR-0025-2020 APPROVED. 50,892 SQ FT TO BE REVIEWED. FOUN | $0 |
| BLDNR-022975-2020 | 2020-12-04 | General construction | 8801 Durant Rd | foundation only | $6,563,250 |
| BLDNR-021320-2020 | 2020-06-17 | General construction | 8801 Durant Rd | Construct MSE Retaining Wall #6 | $0 |
| BLDNR-021314-2020 | 2020-06-17 | General construction | 8801 Durant Rd | Construct MSE Retaining Wall #2 | $0 |
| BLDNR-021313-2020 | 2020-06-17 | General construction | 8801 Durant Rd | Construct MSE Retaining Wall #1 | $0 |
| BLDNR-021319-2020 | 2020-06-17 | General construction | 8801 Durant Rd | Construct MSE Retaining Wall #5 | $0 |
| BLDNR-021317-2020 | 2020-06-17 | General construction | 8801 Durant Rd | Construct MSE Retaining Wall #4 | $0 |
| BLDNR-017959-2020 | 2020-06-01 | General construction | 8801 Durant Rd | temp electrical panel and service for construction temp office trailer for construction use only | $0 |
| BLDNR-009481-2020 | 2020-05-18 | General construction | 1101 Nowell Rd | ALT Huber 1ST & 2ND FLOORS BUS-OCC, II-B CONST, 2 STORY 23413 sf BLDG, 16,622sf TBR New wall and doo | $1,835,734 |
| BLDNR-016725-2019 | 2019-11-07 | General construction | 2300 Capital Summit Ct | ADDITION/LEITH ACURA - Addition of electrical room, riser room and court for the relocation of equip | $56,342 |
| 157996 | 2019-08-19 | General construction | 7112 SANDY FORKS RD | 1876 SF Addition to ABC Store | $141,901 |
| 147289 | 2019-06-25 | General construction | 10440 FOSSIL CREEK CT | FIRE STATION | $0 |
| 156709 | 2019-04-05 | General construction | 1 EXCHANGE PLZ | INSTALL PEDESTRIAN GATE | $0 |
| 156708 | 2019-04-01 | General construction | 2302 CAPITAL SUMMIT CT | TEMPORARY CONSTRUCTION TRAILER | $0 |
| 156336 | 2019-03-28 | General construction | 2351 CAPITAL SUMMIT CT | TEMPORARY CONSTRUCTION TRAILER | $0 |
| 155215 | 2019-02-21 | General construction | 2300 CAPITAL SUMMIT CT | LEITH ACURA NEW DEALERSHIP | $3,236,482 |
| 155004 | 2019-02-08 | General construction | 2350 CAPITAL SUMMIT CT | LEITH LINCOLN | $2,860,280 |
| 154348 | 2019-01-28 | General construction | 6108 FALLS OF NEUSE RD | CHANGE OF USE TENNANT UPFIT. | $98,776 |
| 153091 | 2018-12-11 | General construction | 5601 CAPITAL BLVD | LEITH DETAIL SHOP | $195,836 |
| 151021 | 2018-11-30 | General construction | 4001 CAPITAL HILLS DR | JAGUAR /LANDROVER PARKING LOT | $0 |
| 152376 | 2018-11-21 | General construction | 4001 CAPITAL HILLS DR | 17 NEW LIGHT POLES AND BASES (PARKING LOT LIGHTING | $0 |
| 153729 | 2018-11-19 | General construction | 5800 OAK FOREST DR | LEITH WHOLESALE PARTS | $141,925 |
| 150326 | 2018-07-25 | General construction | 5500 CAPITAL BLVD | ALTERATIONS/REPAIRS PHASE 3 OF 3 | $736,602 |
| 150009 | 2018-07-25 | General construction | 5500 CAPITAL BLVD | ALT/LEITH JEEP PH 2 | $355,322 |
| 148960 | 2018-05-15 | General construction | 5500 CAPITAL BLVD | LEITH JEEP - PHASE 1 PARTS DEPARTMENT | $248,054 |
| 148218 | 2018-04-25 | General construction | 5424 CAPITAL BLVD | SALES TRAILER/LEITH JEEP | $150,342 |
| 147739 | 2018-03-27 | General construction | 3940 CAPITAL HILLS DR | CONSTRUCT OFFICES IN SHOWROOM | $17,641 |
| 140544 | 2018-03-22 | General construction | 221 S ROGERS LN | INSTALL PALLET RACKS | $10,700 |
| 145609 | 2018-02-26 | General construction | 2350 CAPITAL SUMMIT CT | CONSTRUCT MSE RETAINING WALL | $0 |
| 145279 | 2018-02-16 | General construction | 4415 PLEASANT GROVE CHURCH RD | PLEASANT GROVE UNITED METHODIST | $330,445 |
| 145278 | 2018-02-16 | General construction | 4415 PLEASANT GROVE CHURCH RD | STORAGE ROOM ADDITION | $113,692 |
| 145276 | 2018-02-16 | General construction | 4415 PLEASANT GROVE CHURCH RD | WELCOME CENTER ADDITION | $330,445 |
| 145162 | 2017-12-05 | General construction | 5610 OAK FOREST DR | LEITH ADMINISTRATION TRAILER | $299,230 |
| 144416 | 2017-11-09 | General construction | 5420 CAPITAL BLVD | CANOPY AT AUTO DEALERSHIP | $265,898 |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Source and limits
Public Raleigh permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →