COMPANY RECORD · NEW ORLEANS, LA
Gibbs Construction — permit history in New Orleans, LA
Gibbs Construction appears on 34 New Orleans permit records from 2016 through 2026, most often general construction (82.4% of the record).
Permit categories
| Category | Permits | Share |
|---|---|---|
| General construction | 28 | 82.4% |
| Demolition | 4 | 11.8% |
| Mechanical / HVAC | 2 | 5.9% |
3 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.
Activity by year
| Year | Permits issued |
|---|---|
| 2016 | 3 |
| 2017 | 2 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 5 |
| 2022 | 2 |
| 2023 | 10 |
| 2024 | 3 |
| 2025 | 5 |
| 2026 | 2 |
Busiest year on record: 2023, with 10 permits. One project can account for several filings, so read this as filing activity rather than workload.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 4300 Mandeville St | 2026-06-18 |
| 4460 Dauphine St | 2026-05-28 |
| 639 Loyola Ave, 10th Floor | 2025-10-24 |
| 639 Loyola Ave | 2025-04-22 |
| 1001 Howard Ave | 2025-04-15 |
| 801 S Norman C Francis Pkwy | 2025-03-31 |
| 717 Orleans Ave | 2025-03-26 |
| 1025 S Norman C Francis Pkwy | 2024-10-11 |
| 8300 Earhart Blvd Ste 101 | 2024-03-05 |
| 1001 S Norman C Francis Pkwy | 2023-08-24 |
| 1522 Chippewa St | 2023-08-02 |
| 1220 Spain St | 2023-07-24 |
| 2901 S Carrollton Ave | 2023-06-30 |
| 425 Elysian Fields Ave | 2023-05-22 |
28 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $12,462,885, median $467,044. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Permits on record
34 permits; open the full list
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| 26-15087-DEMO | 2026-06-18 | Demolition | 4300 Mandeville St | DEMOLITION OF THE EXISTING FIELDHOUSE AND ASSOCIATED SITE ELEMENTS AT FARLEY FIELD IN PREPARATION FOR THE REDEVELOPMENT OF THE SITE INTO A NEW ATHLETIC COMPLEX WITH MULTI-SPORT FIE | $0 |
| 25-38294-DEMI | 2026-05-28 | General construction | 4460 Dauphine St | Interior non structural demo and debris removal. To be done as per scope. NOT FOR USE OR OCCUPANCY. RENOVATION REQUIRES A SEPARATE PERMIT. Failure to secure the proper permits o | $998,897 |
| 25-27124-RNVN | 2025-10-24 | General construction | 639 Loyola Ave, 10th Floor | Minor interior reconfiguration/renovation of an office space on the 10th floor. | $1,399,148 |
| 25-10642-DEMI | 2025-04-22 | General construction | 639 Loyola Ave | interior demolition on 22nd floor No use or occupancy. Renovation requires a separate permit. Failure to secure the proper permits or proceed with work outside the scope of thi | $178,492 |
| 25-10416-DEMI | 2025-04-15 | General construction | 1001 Howard Ave | remove mechanical equipment and loose debris from the roofs of the 9th, 18th, and 19th floors; remove all exterior glass from the stair tower located at the corner of South Rampart | $438,686 |
| 25-02207-HVAC | 2025-03-31 | Mechanical / HVAC | 801 S Norman C Francis Pkwy | Renovation of the Xavier Living Learning Center dormitory building. Includes re-work of building exhaust ductwork and the addition of new mechanical equipment. The mechanical equip | $525,985 |
| 23-23949-RNVN | 2025-03-26 | General construction | 717 Orleans Ave | Partial Roof Replacement, New Doors, Balcony Modification | $571,890 |
| 24-30222-RNVS | 2024-11-22 | General construction | 801 S Norman C Francis Pkwy | THE INTENT OF THIS PROJECT IS TO PERFORM INTERIOR AND EXTERIOR REPAIRS RESULTING FROM A COMBINATION OF FOUNDATION AND ENVELOPE ISSUES. THE SCOPE OF WORK INCLUDES: PILE REPAIR o | $525,985 |
| 24-22084-RNVN | 2024-10-11 | General construction | 1025 S Norman C Francis Pkwy | Partial roof replacement. Remove and replace the mod bit roofing on a portion of the building. | $1,049,511 |
| 23-16037-RNVN | 2024-03-05 | General construction | 8300 Earhart Blvd Ste 101 | Tenant Buildout of existing interior space into a veterinary dental clinic | $998,393 |
| 23-16468-RNVN | 2023-08-24 | General construction | 1001 S Norman C Francis Pkwy | Mechanical repairs and equipment replacement. Repair/replace finishes damaged by mechanical equipment failures. | $8,931,634 |
| 23-17168-DEMI | 2023-08-07 | General construction | 1001 S Norman C Francis Pkwy | Interior Demo ONLY. No use or occupany. Renovation requires separate permit. | $432,485 |
| 23-16944-RNVN | 2023-08-02 | General construction | 1522 Chippewa St | Classroom expansion at St. Michael Special School, hvac, electrical, plumbing | $97,000 |
| 22-36219-ACCS | 2023-07-24 | General construction | 1220 Spain St | Replacement of existing diesel generator with new larger natural gas generator. Modification of existing electrical system to accept new generator. | $276,000 |
| 23-17351-HVAC | 2023-06-30 | Mechanical / HVAC | 2901 S Carrollton Ave | Mechanical Permit for 120' of Duct Alteration | $64,383 |
| 23-12948-RNVN | 2023-06-01 | General construction | 2901 S Carrollton Ave | INTERIOR RENOVATION OF EXISTING CHAPEL. MODIFICATION OF DUCTWORK AND REPLACEMENT OF WAINSCOTTING. | $849,000 |
| 23-08869-RNVN | 2023-05-22 | General construction | 425 Elysian Fields Ave | Exterior facade cleaning and repairs | $661,210 |
| 23-07602-RNVN | 2023-05-19 | General construction | 425 Elysian Fields Ave | Reroofing low sloped roof of existing 2 story Entergy Claiborne Substation | $495,403 |
| 22-32387-NEWC | 2023-05-11 | General construction | 4401 Elysian Fields Ave | 3,470 SF Non-enclosed batting practice facility. | $1,190,000 |
| 23-09786-DEMI | 2023-04-18 | General construction | 231 Carondelet St | The Anticipated Scope of Work is: a. Removal of existing ceiling tile b. Removal of existing furnishings and loose materials c. Selective demolition of non-structural fin | $97,871 |
| 22-31939-RNVN | 2022-10-25 | General construction | 3060 Dauphine St | Pour of a new concrete slab at First Floor Retail Space 112. | $28,000 |
| 22-09213-RNVN | 2022-05-04 | General construction | 1522 Chippewa St | Removal of existing cantilever entrance canopy; installation of new free-standing canopy structure. | $105,835 |
| 21-25891-RNVN | 2021-11-15 | General construction | 316 Chartres St | Work to include flashing, stucco, and roof repairs, to address water intrusion issues at orange-rated buildings, per attached materials stamped VCC approved 11/11/2021. | $997,106 |
| 20-34603-RNVS | 2021-07-30 | General construction | 5435 Laurel St | REHABILITATION OF AN HISTORIC COMMERCIAL BUILDING CIRCA 1896. SCOPE INCLUDES TENANT EXPANSION OF "OCTAVIA BOOKS" WITHIN EXISTING BUILDING AS NEW TENANT - NO CHANGE IN OCCUPANCY; AN | $2,050,146 |
| 21-13615-RNVN | 2021-06-03 | General construction | 541 Bourbon St | We will be replacing11of the approximately 100 balcony doors. The doors that are being replaced are rotting out. The replacement doors are to be an exact match to the existing – co | $28,000 |
| 21-13733-RNVN | 2021-06-01 | General construction | 541 Bourbon St | Sheraton Hotel upgrades - Replacement of interior finishes and furniture including paint, wall covering, carpet and bedroom furniture at bedrooms and hallways on floors 2-5. Instal | $1,304,197 |
| 20-43126-RNVN | 2021-02-19 | General construction | 6501 Berkley Dr | Interior renovation and site improvements as per plans. | $12,462,885 |
| 20-27483-RNVS | 2020-05-21 | General construction | 1100 Royal St | Structural repairs to the masonry at the first floor of the Royal and Ursuline corner of the building per Architecture Committee approval of 4/8/20 and materials stamped VCC approv | $130,000 |
| 19-10371-DEMO | 2019-05-30 | Demolition | 6001 Magazine St | Demo of slab | $0 |
| 17-34434-DEMI | 2017-10-12 | General construction | 5300 Tchoupitoulas St, Suite C | Demolition of existing interior space consisting of interior non-structural walls and existing MEP work. | $38,225 |
| 16-36002-DEMO | 2017-01-04 | Demolition | 700 Magazine St | HDLC - Demolition of an existing steel frame metal structure. | $40,000 |
| 16-33988-DEMO | 2016-11-08 | General construction | 640 Magazine St | Gutting of existing structure to accommodate change of use as per HDLC approval. | $597,656 |
| 16-25461-DEMI | 2016-08-04 | General construction | 1104 Decatur St | Interior demolition of existing restaurant and bar. Plans submitted for renovation under 16-22416-RNVN. | $21,000 |
| 16-16696-DEMO | 2016-06-21 | Demolition | 1010 N Galvez St | Demolition of two, one-story buildings, to grade, as per site plan approved 6/20/16. Site shall be leveled and cleared of all debris. 2. All changes or additional work must be app | $1,000 |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Source and limits
Public New Orleans permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →