COMPANY RECORD · BOULDER, CO

Sturgeon Electric Company Inc — permit history in Boulder, CO

Sturgeon Electric Company Inc appears on 109 Boulder permit records from 2015 through 2026, most often electrical (89% of the record).

Permit categories

CategoryPermitsShare
Electrical9789%
Fire protection1211%

2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.

Activity by year

YearPermits issued
20157
201611
201711
20189
201911
20206
202111
202211
202313
202413
20254
20262

Busiest year on record: 2023, with 13 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
1600 COMMERCE ST2026-06-26
3450 MITCHELL LN2026-02-09
5445 CONESTOGA CT2025-09-15
3200 PEARL ST2025-08-05
1644 CONESTOGA ST2025-03-04
2930 BROADWAY2024-09-09
3052 STERLING CIR2024-07-26
6333 LOOKOUT RD2024-06-28
5200 PEARL ST2024-06-18
1805 33RD ST2024-06-11
5064 PEARL ST2024-06-07
1720 13TH ST2024-05-08
1499 CANYON BLVD 1/22024-04-29
2800 JAY RD 1/22024-04-09

96 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $0 to $1,159,916, median $2,500. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

109 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
FIR2026-002232026-06-26Fire protection1600 COMMERCE STFire Alarm Permit$9,827
FIR2025-005042026-02-09Fire protection3450 MITCHELL LNFull Fire Alarm Replacement in buildings FL1, FL2, & FL3. (FAN)$1,159,916
ELE2025-010232025-10-14Electrical3450 MITCHELL LNAdditional Electrical Circuits for Fire Alarm System$10,000
ELE2024-004722025-09-15Electrical5445 CONESTOGA CTInstall electrical infrastructure to add EV Chargers to parking lot. Scope includes installing utility meter housing, utility meter disconnect, low volt panel, EV Charger disconnec$30,000
ELE2025-007032025-08-05Electrical3200 PEARL STReissuance of permit ELE2023-00868 that was voided due to 180 days inactivity. Install Electrical Infrastructure to add EV Chargers to Parking Lot. Scope includes installing utilit$20,000
ELE2024-001482025-03-04Electrical1644 CONESTOGA ST**Revised plans and parking layout 3/10/26** Install electrical infrastructure to add EV Chargers to parking area. Scope includes installing utility meter disconnect, utility mete$15,000
ELE2024-002982024-09-09Electrical2930 BROADWAYInstall electrical infrastructure to add EV Chargers to parking garage. Scope includes installing a meter disconnect, Utility meter housing, low volt panel, EV Chargers, pipe and w$15,000
ELE2024-006062024-07-26Electrical3052 STERLING CIRInstall electrical infrastructure to add EV Chargers to the parking lot. Scope includes installing utility meter housing, utility meter disconnect, low volt panel, EV Charger disco$10,000
ELE2024-001982024-06-28Electrical6333 LOOKOUT RDInstall electrical infrastructure to add EV chargers to parking area. Scope includes install utility meter housing, utility CT cabinet, low volt panel, EV Charger disconnects, pipe$15,000
ELE2024-003372024-06-18Electrical5200 PEARL STInstall electrical infrastructure to add EV Chargers to parking lot. Scope includes installing Utility meter housing, meter disconnect, low volt panel, EV Charger disconnects, pipe$15,000
ELE2024-003352024-06-11Electrical1805 33RD STInstall electrical infrastructure to add EV Chargers to parking lot. Scope includes installing Utility meter housing, meter disconnect, low volt panel, EV charger disconnects, EV C$15,000
ELE2024-003362024-06-07Electrical5064 PEARL STInstall Electrical infrastructure to add EV Chargers to parking lot. Scope includes installing Utility meter housing, Utility CT cabinet, high volt panel, pipe and wire.$15,000
ELE2024-003302024-05-08Electrical1720 13TH STInstall electrical infrastructure to add EV Chargers to parking lot. Scope includes installing Utility meter housing, meter disconnect, Low Volt panel, EV Chargers, pipe and wire.$17,000
ELE2024-002042024-04-29Electrical1499 CANYON BLVD 1/2Installing a new metered service for red light cameras 120/240v 70amp single phase service$2,500
ELE2024-002052024-04-09Electrical2800 JAY RD 1/2Installing a new metered service for red light cameras 120/240v 70amp single phase service$2,500
ELE2024-001202024-02-23Electrical1600 RANGE STInstall electrical infrastructure to add EV Chargers to parking area. Scope includes installing Meter disconnect, Meter Housing, Low Volt Panel, EV Chargers, Pipe and Wire. ****10/$10,000
ELE2024-001132024-02-16Electrical6400 ARAPAHOE RDInstall Electrical Infrastructure to add EV Chargers to Parking area. Scope includes installing Utility Meter Housing, Meter Disconnect, High Volt Panel, EV Charger Disconnects, Pi$10,000
ELE2024-000742024-02-07Electrical5050 PEARL STInstall Electrical infrastructure to add EV Chargers in parking area. Scope includes installing Utility Meter Housing, Utility CT Cabinet, Low Volt Panel, EV Chargers, Pipe and Wir$15,000
ELE2024-000802024-02-07Electrical5311 WESTERN AVEInstall Electrical Infrastructure to add EV Chargers to parking lot. Scope includes installing Meter Disconnect, Utility Meter Housing, Low Volt Panel, EV Chargers, Pipe and Wire.$15,000
ELE2023-009532023-11-14Electrical1140 PORTLAND PL 002Install electrical infrastructure to add EV chargers to parking area. scope includes installing meter housing, CT cabinet, low volt panel, EV chargers, pipe and wire.$50,000
ELE2023-008892023-09-08Electrical2855 63RD STInstall electrical infrastructure to add EV chargers to parking area. Scope includes installing meter housing, CT cabinet, Switchboard, pipe and wire. ***7/361/24*** Breaker and wi$25,000
ELE2023-008682023-09-01Electrical3200 PEARL STVOID-180 Days no activity Install electrical infrastructure to add EV chargers. Scope includes installing meter housing, utility CT section, disconnect, transformer, pipe and wire.$20,000
ELE2023-008062023-08-14Electrical6025 ARAPAHOE RDInstall electrical infrastructure to add EV chargers on the interior and exterior of building. Scope includes installing meter housing, CT cabinet, low volt panels, high volt panel$25,000
ELE2023-007202023-07-28Electrical3001 SPRUCE STInstall electrical infrastructure to add EV Chargers. Scope includes installing meter housing, adding breaker to existing gear, install transformer, Low Volt panel, disconnects, ch$10,000
ELE2023-006992023-07-24Electrical6304 SPINE RDInstall electrical infrastructure to add EV Chargers in south west parking area. Sturgeons scope includes installing a disconnect, meter housing, Low Volt Panel, EV Chargers, pipe $10,000
ELE2023-005942023-06-27Electrical2285 28TH ST*Voided for inactivity - no inspections within 180 days* Install Electrical infrastructure for 2 added EV Chargers, installed by 3rd party. Sturgeons scope to install a disconnect,$5,000
ELE2023-004562023-05-16Electrical560 MOHAWK DRINSTALLATION OF A NEW SECONDARY METERED SERVICE (225A 3PH 208/120) TO EXCLUSIVELY FEED ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE TO COVER INSTALLATION OF SECONDARY SERVICE O$15,000
ELE2022-014152023-05-03Electrical4905 OSAGE DRINSTALLATION OF A NEW SECONDARY SERVICE (225A 3PH 208/120) TO FEED ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE TO COVER INSTALLATION OF SECONDARY SERVICE ONLY, ELECTRIC VEH$2,500
ELE2023-003432023-04-21Electrical5550 AIRPORT BLVDThe scope of work is as follows: 1) Remove (2) existing boiler fans, conduit, and conductors back to motor control centers. 2) Relocate spare 150A bucket from MCC-Y-105 to MCC-Y-10$80,000
ELE2022-015392023-01-17Electrical1201 1/2 30TH ST**Void for 180 days of Inactivity** New LCC that has 3 meters on it to run the traffic signal at 30th and Colorado and new underpass lights and irrigation controller$3,500
ELE2022-014412023-01-12Electrical4827 THUNDERBIRD DRINSTALLATION OF NEW SECONDARY SERVICE (225A 3PH 208/120) TO FEED ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE TO COVER SECONDARY SERVICE ONLY, ELECTRIC VEHICLE CHARGING STATION$2,500
ELE2022-014382023-01-12Electrical4920 THUNDERBIRD CIRINSTALLATION OF NEW SECONDARY SERVICE (225A 3PH 208/120) TO FEED ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE TO COVER SECONDARY SERVICE ONLY, ELECTRIC VEHICLE CHARGING STATION$2,500
ELE2022-014732022-11-15Electrical2419 COLORADO AVEINSTALLATION OF A NEW SECONDARY SERVICE (225A 1PH 208/120) TO FEED ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE TO COVER INSTALLATION OF SECONDARY SERVICE ONLY, ELECTRIC VEHI$2,500
ELE2022-010902022-09-19Electrical4775 1/2 BROADWAYInstalling a new 120/240v single phase 100amp service to run the traffic signal at Broadway and Lee Hill$2,000
ELE2022-005462022-09-14Electrical4775 WALNUT STCurrent tenant of Suite 1B expansion into adjacent tenant space as indicated on plan with inpacted areas of construction being approximately 1767 sf. No exterior building improveme$350,000
ELE2022-010882022-09-09Electrical4481 1/2 BROADWAYInstalling a new LCC that has two meters on the back of it. One meter is to run the underpass lights and the second meter is to run the Irrigation controller. Both 120/240v 100amp $2,500
ELE2022-010802022-09-09Electrical4395 1/2 BROADWAYNew 120/240v single phase 100amp meter install to run Intersection of Broadway and Violet$2,500
ELE2022-011542022-08-16Electrical4880 1/2 ARAPAHOE AVEInstalling a new 120/240v 100amp single phase meter to run the traffic signal at Arapahoe Ave and Commerce St$2,000
ELE2022-010892022-08-11Electrical4590 1/2 BROADWAYInstalling a new 120/240v single phase 100amp meter to run new traffic signals at Broadway and Yarmouth$2,000
ELE2022-011062022-08-04Electrical2555 30TH ST*Voided for inactivity - no inspections within 180 days* INSTALLATION OF NEW 400A 3PH 480/277 METERED SERVICE TO FEED ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE TO COVER SEC$2,500
ELE2022-007912022-06-02Electrical5550 AIRPORT BLVDElectrical quick permit including minor demo/moving of 120V convenience outlets and lights.$35,000
ELE2022-005702022-04-26Electrical5550 AIRPORT BLVDINSTALL PREVIOUSLY REMOVED FIRE DAMPER JUNCTION BOX. ROUTE NEW CONDUIT AS SHOWN. MAKE ALL CONNECTIONS AS NOTED DURING REMOVAL. CONNECT NEW CONDUIT TO EXISTING CONDUIT. INSTALL PREV$1,000
ELE2022-003832022-04-07Electrical6400 ARAPAHOE RD EVCHRGNEW 225A METERED SERVICE TO SERVE ELECTRIC VEHICLE CHARGING STATIONS. PERMIT SCOPE COVERS SECONDARY SERVICE ONLY, VEHICLE CHARGER PEDESTAL NOT INCLUDED IN SCOPE.$2,500
ELE2021-016602021-10-18Electrical5550 AIRPORT BLVDProvide 120V power for temporary Construction Connex.$1,000
ELE2021-014952021-09-28Electrical1775 YAUPON AVE*Voided for inactivity - no inspections within 180 days* New 100A Metered Service to feed electric vehicle charging stations. Metered service ONLY, charging pedestal to be install$2,250
ELE2021-010942021-07-16Electrical7100 1/2This permit is for the meter disconnect service at 71st and Lookout Rd. The address for the meter is 7100.5 Lookout Rd.$2,500
ELE2021-004422021-07-02Electrical3825 WALNUT STNew metered service installation to serve electric vehicle charging stations for a private business. Associated with FLD2021-00024.$2,250
ELE2021-009502021-06-30Electrical325 BROADWAYInstallation of new electrical meter for intersection at Broadway & Rayleigh. The Meter address is 325.5 Broadway. The Meter is mounted right next to the cabinet.$2,500
ELE2021-005132021-05-07Electrical1500 PEARL ST*Voided for inactivity - no inspections within 180 days* New metered service for electric vehicle charging stations$2,250
ELE2020-017892021-04-13Electrical5550 AIRPORT BLVD*COVID RESPONSE-RELATED* Connect Electrical service to temporary trailer, related to CTR2020-00004$7,000

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Boulder permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →