COMPANY RECORD · BOULDER, CO

Groundworks Colorado DBA Complete Basement Systems — permit history in Boulder, CO

Groundworks Colorado DBA Complete Basement Systems appears on 140 Boulder permit records from 2015 through 2026, most often general construction (91.4% of the record).

Permit categories

CategoryPermitsShare
General construction12891.4%
Electrical128.6%

2 categories, as classified by the issuing authority. Small categories stay visible rather than being rounded away.

Activity by year

YearPermits issued
20152
201614
201713
20187
201911
20209
202117
202220
202313
202417
20257
202610

Busiest year on record: 2022, with 20 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
1936 BLUFF ST2026-08-03
2550 VASSAR DR2026-07-06
810 37TH ST2026-06-12
2825 ELM AVE2026-05-22
620 IRIS AVE2026-05-15
370 S 45TH ST2026-05-14
3605 CONIFER CT2026-05-11
5300 CYPRESS DR2026-04-16
1224 MARIPOSA AVE2026-03-12
1225 EAST RIDGE AVE2026-02-04
4691 INGRAM CT2025-12-15
1270 AIKINS WAY2025-11-25
2120 GODDARD PL2025-08-28
4202 MONROE DR C2025-08-28

129 distinct addresses on record; the 14 most recent are shown. Declared value on record runs from $540 to $104,193, median $10,928. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

140 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
BLD-SFD2026-004282026-08-03General construction1936 BLUFF STInstall (9) helical piers around the SW foundation to help mitigate further vertical movement of this area.$33,299
BLD-SFD2026-003452026-07-06General construction2550 VASSAR DRInstall (4) helical piers under the SE foundation, as shown on the attached plans, to help mitigate future vertical movement of that area. Work Area: hole for pier (3'x 3' = 9' x$9,500
BLD-SFD2026-002722026-06-12General construction810 37TH STFoundation repair for single family detached dwelling - Scope includes install (4) new Intellijack monoposts and cast-in-place concrete footers under the crawlspace main beam, as s$12,204
BLD-SFD2026-002792026-05-22General construction2825 ELM AVEInstall (6) helical piers under the NE corner of the crawlspace foundation to help mitigate future vertical movement of that area for single family detached dwelling Work Area: h$18,706
BLD-SFD2026-002662026-05-15General construction620 IRIS AVEInstall (4) helical piers under the NW crawlspace foundation to help mitigate future vertical movement of that area. Work Area: Pier holes (2'x 2' = 4' x Qty.4) = 16' square fe$17,330
BLD-SFD2026-002542026-05-14General construction370 S 45TH STInstall (10) push piers around the north (left) side of the crawlspace foundation to help mitigate future vertical movement of that area. Work Area: Pier holes (2'x 2' = 4' x Qt$24,007
BLD-SFD2026-002272026-05-11General construction3605 CONIFER CTInstall (4) push piers under the NW corner of the garage foundation to help mitigate future vertical movement of that area. Work Area: Pier holes (2'x 2' = 4' x Qty.4) = 16' sq$10,136
BLD-SFD2026-001782026-04-16General construction5300 CYPRESS DRInstall (6) helical piers under the the east corner of the crawlspace foundation to help mitigate future vertical movement of that area. Work Area: helical pier holes (2'x 2' = $15,932
BLD-SFD2026-001202026-03-12General construction1224 MARIPOSA AVEInstall (3) helical piers under the south center (rear) foundation (as shown on the attached plans) to help mitigate future vertical movement of these areas. Work Area: helical p$9,302
BLD-SFD2026-000522026-02-04General construction1225 EAST RIDGE AVEInstall (7) push piers around the garage foundation and (4) push piers around the SE basement foundation to help mitigate future vertical movement of these areas. Work Area: push$27,990
BLD-SFD2025-005422025-12-15General construction4691 INGRAM CT***VOID-180 Days no activity*** Install (11) helical piers under the north side of basement foundation to help mitigate future vertical movement of that area. Work Area: helical $31,092
BLD-SFD2025-005162025-11-25General construction1270 AIKINS WAYInstall (7) wall anchors on the rear (south) basement foundation wall to help mitigate future lateral movement of that area. Work Area: wall anchors (16' per anchor x Qty.7) = $11,046
BLD-SFD2025-003362025-08-28General construction2120 GODDARD PLInstall (6) carbon fiber straps vertically on the NW basement foundation wall to help mitigate future lateral movement of that area. Work Area: Carbon Fiber straps (0.4' x 8' = $5,488
BLD-SFD2025-003302025-08-28General construction4202 MONROE DR CInstall two (2) IntelliJack monopost with CIP Concrete footings under the existing main load beam in crawl space, as shown on the attached sketch, to stabilize/level the floor fram$3,092
BLD-SFD2025-002892025-08-04General construction1577 NORTH STInstall (4) helical piers under the NW inside foundation wall to help mitigate future vertical movement of that area.. Work Area: pier holes (2' x 2' = 4' x Qty.7 holes) = 16' $11,965
BLD-SFD2025-002862025-07-28General construction5354 MUIRFIELD CTInstall (7) wall anchors on the east foundation wall to help mitigate future lateral movement of that area. Work Area: wall anchor holes (2' x 3' = 6' x Qty.7 holes) = 42' squa$8,153
BLD-SFD2025-001912025-05-29General construction3195 E EUCLID AVEInstall (9) push piers around the east crawlspace foundation to help mitigate future vertical movement of that area. Work Area: push pier holes (2' x 2' = 9' x Qty.4 holes) = $19,811
BLD-SFD2024-005252024-12-18General construction780 33RD STInstall (4) push piers under the NE corner of the crawlspace foundation to help mitigate future vertical movement of these areas. Work Area: push pier holes (2'x 2' = 4' x Qty.4 $8,583
BLD-SFD2024-004962024-12-10General construction345 30TH STInstall (6) helical piers under the west crawlspace foundation and (6) helical piers under the north crawlspace foundation to help mitigate future vertical movement of these areas.$29,949
BLD-SFD2024-004642024-11-27General construction1321 5TH STInstall (5) helical piers to stabilize the garage foundation. Replace shims with intellijack monopost supported by (1) helical pier and new concrete pier cap. Work Area: push pier$19,699
BLD-SFD2024-004202024-10-29General construction460 S 45TH STInstall (2) push piers under the SE garage foundation and (6) push piers under the NW crawlspace / basement foundation to help mitigate future vertical movement in these areas. Wo$18,355
BLD-SFD2024-004242024-10-29General construction925 34TH STInstall (4) push piers under the SW foundation to help mitigate future vertical movement in these areas. Install carbon fiber strips on the SW corner of the foundation wall to stab$13,372
BLD-SFD2024-003902024-10-10General construction2520 PANORAMA AVE***VOID-180 Days no activity*** Install (22) new helical piers under the foundation walls as shown in the attached plans set to help mitigate future vertical movement in these area$60,912
BLD-SFD2024-003742024-09-26General construction783 13TH ST***10/28/24 *** Withdrawn found that the bedrock is too shallow to install piers Install six (6) helical piers on the south crawlspace foundation to help mitigate vertical movemen$15,465
BLD-SFD2024-003522024-09-10General construction3845 CLOVERLEAF DRInstall six (6) push piers on the SE basment foundation to help mitigate vertical movement. Work Area: push pier holes (3'x 3' = 9' x Qty.6 holes) = 54' square feet.$13,997
BLD-SFD2024-003472024-09-10General construction3538 22ND STInstall two (2) IntelliJack monoposts on existing beam in crawlspace to provide additional support to existing framing system$2,203
BLD-SFD2024-003082024-08-13General construction4530 OSAGE DRInstall (11) push piers under the south basement foundation to help mitigate vertical movement.$30,498
BLD-SFA2024-000182024-07-23General construction1932 PEARL ST BInstall four (4) helical piers under the NE foundation to help mitigate vertical movement. Work Area: (Condo) Slab on grade shallow foundation footer (2'x 2' = 4' x Qty.4 holes) =$10,310
BLD-SFD2024-002142024-06-11General construction2378 DENNISON LNInstall ten (10) push piers around the east crawlspace foundation to help mitigate vertical movement. Install supplemental S4 beam with 3 intellijack monopost supports mid span in $28,422
BLD-SFD2024-002102024-06-04General construction3395 E AURORA AVEInstall seven (7) helical piers on the SW corner of the crawlspace foundation to help mitigate vertical movement. Work Area: Pier install in the crawlspace with shallow footer (2'$15,408
BLD-SFD2024-001662024-05-22General construction1616 NORTH STInstall five (5) push piers on the south crawlspace foundation to help mitigate vertical movement. Work Area: push pier install in the crawlspace, shallow footer (2'x 2' = 4' x Qt$11,362
BLD-SFD2024-000702024-03-18General construction1420 RIVERSIDE AVEInstall three (3) Grip-Tite RDS-2875 helical piers to provide stability to the foundation of the rear addition structure. Work Area: helical pier install (3'x 3' = 9' x Qty.3 hole$10,810
BLD-SFD2024-000362024-02-20General construction2550 VASSAR DRInstall (2) new helical piers to support the existing deck caissons to help mitigate the future vertical movement of the deck posts in these areas. Install (8) new push piers along$26,724
BLD-NRE2023-002072024-01-19General construction6650 GUNPARK DRInstall (24) new helical piers with pier caps and adjustable steel mono posts along the beam lines in the crawlspace to help mitigate vertical movement in these areas. Install (3) $104,193
BLD-SFD2023-004592023-12-27General construction7341 POSTON WAYRemove the existing (2) monoposts and install (2) new steel adjustable monoposts and (2) new helical piers1 foot away from the existing monopost locations under the main beam line $17,780
BLD-SFD2023-004442023-12-18General construction2705 TABLE MESA CTInstall (10) new helical piers under the following foundation walls to help mitigate future vertical movement$21,394
BLD-SFD2023-004132023-11-21General construction1350 RIVERSIDE AVE***VOIDED DUE TO INACTIVITY OVER 180 DAYS*** Installation of four (4) Grip-Tite Helical Piers along the southwest corner foundation walls to stabilize foundation movement.$9,635
BLD-SFD2023-003952023-11-20General construction1224 MARIPOSA AVEInstall seven (7) Grip-Tite Helical Piers along the northern and eastern foundation walls of the residence to stabilize foundation movement. Work Area: depth for piers 5' (hole 4'$16,880
BLD-SFA2023-000502023-11-08General construction1611 SPRUCE STInstall (16) helical piers under the following foundation walls to help mitigate future vertical movement in these areas: o (6) piers under the north wall o (5) piers under the eas$66,800
BLD-SFD2023-003942023-11-07General construction925 34TH STInstall (5) new push piers under the foundation walls of the southwest corner of the house to help mitigate vertical movement in this area. Install (6) new wall anchors on the east$18,697
BLD-SFD2023-003162023-09-11General construction4720 CHEYENNE CTInstall (4) push piers along the north foundation wall to help mitigate future vertical movement in this area. Work Area: push piers (2'x 2' area) x (Qty. 4) = 16' square feet tot$15,013
BLD-SFD2023-001992023-07-14General construction757 8TH STInstall (12) new push piers along the northern half of the foundation walls to help mitigate vertical movement in this area. Work Area: push piers, footer at frost depth (3'x 3' h$27,482
BLD-SFD2023-001942023-07-12General construction1001 BASELINE RDInstall (18) new helical piers along the northern half of the foundation walls to help mitigate vertical movement in this area. Work Area: helical piers frost depth (3'x 3' hole) $41,603
BLD-SFA2023-000162023-06-09General construction1460 QUINCE AVE S103Install (1) helical pier under the right upper deck post foundation (the only deck post) to help mitigate future vertical movement for this area. Work Area: helical pier (2'x 2' ho$3,410
BLD-SFD2023-000842023-04-03General construction1140 HANCOCK DRInstall (6) push piers under the crawlspace foundation walls to help mitigate future vertical movement in these areas. Install (6) wall braces along the north basement foundation w$21,960
BLD-SFD2023-000702023-03-15General construction3600 BROADWAYStabilize the east basement foundation walls by installing (5) wall braces to help mitigate lateral movement of that area. Work Area: no excavation for wall braces (8' long x 6") $9,784
BLD-SFD2023-000122023-01-13General construction4645 TALBOT DRStabilize the east side foundation by installing (9) push piers to help mitigate vertical movement of that area. Work Area: excavation for push piers (3' x 3') x (Qty. 9) = 81' sq$26,888
BLD-SFD2022-005412022-12-12General construction4380 DREW CIRInstall (3) new steel mono posts with new concrete pad footings under the mudroom subfloor at the front of the house to support the floor and help mitigate future vertical movement$8,638
BLD-SFD2022-005572022-12-12General construction780 HARTFORD DRInstall (9) push piers along the foundation walls to help mitigate future vertical movement: Work area: excavation for push piers (3'x3')x(Qty. 9) =81' square feet$21,050
BLD-SFD2022-005212022-12-01General construction1224 MARIPOSA AVEStabilize the SE foundation by installing (6) helical piers to help mitigate vertical movement of that area. Work Area: excavation for helical piers at 3' deep is (3' x 3') x (Qty$20,301

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Boulder permit records through 2026, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →