Sunergy Systems Inc. — permit history in Seattle, WA

Sunergy Systems Inc. appears on 175 Seattle permit records from 2015 through 2025, all of them electrical.

Permit categories

CategoryPermitsShare
Electrical175100%

Activity by year

YearPermits issued
201557
201653
201744
201820
20251

Busiest year on record: 2015, with 57 permits. One project can account for several filings, so read this as filing activity rather than workload.

Where they worked

Address in sourceMost recent permit
3118 W GOVERNMENT WAY2025-10-06
1217 FEDERAL AVE E2018-04-26
12005 7TH AVE NW2018-04-25
13564 39TH AVE NE2018-04-20
3112 E HARRISON ST2018-04-06
1225 NE 104TH ST2018-04-02
522 32ND AVE S2018-03-27
1221 3RD AVE N2018-03-22
4317 5TH AVE NW2018-03-15
6921 ROOSEVELT WAY NE2018-03-15
3029 FAIRMOUNT AVE SW2018-03-14
1531 CHERRYLANE PL S2018-03-08
7135 BEACH DR SW2018-03-02
1428 36TH AVE2018-02-16

156 distinct addresses on record; the 14 most recent are shown. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.

Permits on record

175 permits; open the 50 most recent
PermitIssuedCategoryAddress in sourceScope as filedDeclared value
7109674-EL2025-10-06Electrical3118 W GOVERNMENT WAYPHOTOVOLTAIC PITCHED ROOF MOUNTED SYSTEM6.300 KW DC/6.020 KW AC/5.719 KW CEC AC& ENERGY STORAGE SYSTEM - 15 KWH [10/6/25 BGO - Approved PV+ESS Plan Set]$47,712
6658795-EL2018-04-26Electrical1217 FEDERAL AVE E[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6658441-EL2018-04-25Electrical12005 7TH AVE NW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6657596-EL2018-04-20Electrical13564 39TH AVE NE50A NEMA 14-50 RECEPTACLE IN GARAGE FOR ON-BOARD CAR CHARGER
6655413-EL2018-04-10Electrical13564 39TH AVE NE[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6654970-EL2018-04-06Electrical3112 E HARRISON ST[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6653998-EL2018-04-02Electrical1225 NE 104TH ST[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6652814-EL2018-03-27Electrical522 32ND AVE SINSTALL CUSTOMER PURCHASED EV CHARGER
6652216-EL2018-03-22Electrical1221 3RD AVE NINSTALL NEMA 14-50 OUTLET ON 30A CIRCUIT AND BREAKER.
6650921-EL2018-03-15Electrical4317 5TH AVE NW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6650859-EL2018-03-15Electrical6921 ROOSEVELT WAY NE[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6650621-EL2018-03-14Electrical3029 FAIRMOUNT AVE SW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6649543-EL2018-03-08Electrical1531 CHERRYLANE PL SINSTALLATION OF NEMA 14-50 RECEPTACLE IN GARAGE
6648353-EL2018-03-02Electrical7135 BEACH DR SW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6646131-EL2018-02-16Electrical1428 36TH AVE[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6645499-EL2018-02-14Electrical1808 12TH AVE S[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6643038-EL2018-01-31Electrical6747 PALATINE AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6641314-EL2018-01-22Electrical830-B 15TH AVE[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6639930-EL2018-01-12Electrical6604 HIGH POINT DR SWA ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQUI
6639582-EL2018-01-11Electrical9745 DAYTON AVE NRUN 50A CIRCUIT FOR NEMA 14-50 RECEPTACLE IN GARGAGE FOR EV CHARGER.
6638406-EL2018-01-04Electrical809 N 60TH ST[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6636726-EL2017-12-21Electrical4018 GREENWOOD AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6636429-EL2017-12-20Electrical2511 22ND AVE E[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6633497-EL2017-12-05Electrical3509 MERIDIAN AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6633476-EL2017-12-05Electrical7357 16TH AVE NW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6631570-EL2017-11-21Electrical11733 12TH AVE NE[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6630320-EL2017-11-14Electrical4037 32ND AVE W[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6629415-EL2017-11-09Electrical7049 9TH AVE NW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6629480-EL2017-11-09Electrical2708 NE 135TH ST[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6628305-EL2017-11-03Electrical11517 NORTH PARK AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6626194-EL2017-10-24Electrical116 37TH AVE E[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6626228-EL2017-10-24Electrical8051 CORLISS AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6626296-EL2017-10-24Electrical10017 35TH AVE NEINSTALL CHARGEPOINT EV CHARGER, 40A BREAKER.
6623918-EL2017-10-12Electrical12066 PALATINE AVE NADD SUBPANEL AND 50A 240V CIRCUIT RECEPTACLE
6623423-EL2017-10-10Electrical741 HARVARD AVE E[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6623287-EL2017-10-09Electrical1222 MCGILVRA BLVD E[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6622662-EL2017-10-05Electrical8056 DIBBLE AVE NW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6621322-EL2017-09-27Electrical12066 PALATINE AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6620529-EL2017-09-22Electrical7323 VASHON PL SW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6616806-EL2017-09-01Electrical6242 31ST AVE NEUPGRADE SERVICE TO FROM 125A TO 200A, INCLUDING METER AND SERVICE PANEL. UPGRADE SUBPANEL IN GARAGE TO 80A FEEDERS, TRENCH, 50A RECEPTACLE IN GARAGE.
6614818-EL2017-08-22Electrical6722 EARL AVE NW[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6612050-EL2017-08-07Electrical6242 31ST AVE NE8-25-17 BZ PV review waived per 2017 code new threshold 7.7KVA [A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSP
6611804-EL2017-08-04Electrical4229 7TH AVE NE[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6611412-EL2017-08-03Electrical324 NE 45TH ST[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6611018-EL2017-08-01Electrical5326 KEYSTONE PL N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6609613-EL2017-07-25Electrical8116 14TH AVE SW7-27-17 BZ PV system one-line approved [A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFOR
6609774-EL2017-07-25Electrical222 FAIRVIEW AVE N[A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFORE INSTALLATION BEGINS, BUT AFTER THE EQU
6602405-EL2017-06-13Electrical9021 49TH AVE NEREPAIR/REPLACE METER ENCLOSURE
6600789-EL2017-06-05Electrical2730 BOYER AVE EINSTALL 200A METER MAIN, TURN EXISTING 200A PANEL INTO SUBPANEL FED FROM NEW METER MAIN.
6600029-EL2017-05-31Electrical3937 SW 109TH ST6-13-17 BZ PV system one-line approved [A ONE-LINE DIAGRAM WILL BE REQUIRED ON SITE AT THE TIME OF INSPECTION OF ANY RENEWABLE ENERGY SYSTEM. A COVER INSPECTION IS REQUIRED BEFOR

Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.

Source and limits

Public Seattle permit records through 2025, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →