COMPANY RECORD · DETROIT, MI
3R Home Improvement — permit history in Detroit, MI
3R Home Improvement appears on 246 Detroit permit records from 2019 through 2025, all of them plumbing.
Permit categories
| Category | Permits | Share |
|---|---|---|
| Plumbing | 246 | 100% |
Activity by year
| Year | Permits issued |
|---|---|
| 2019 | 1 |
| 2020 | 38 |
| 2021 | 18 |
| 2022 | 15 |
| 2023 | 19 |
| 2024 | 133 |
| 2025 | 22 |
Busiest year on record: 2024, with 133 permits. One project can account for several filings, so read this as filing activity rather than workload.
Where they worked
| Address in source | Most recent permit |
|---|---|
| 364 Lakewood St | 2025-10-13 |
| 5900 Devonshire Rd | 2025-10-13 |
| 8916 Pinehurst St | 2025-09-30 |
| 7545 Quinn St | 2025-09-30 |
| 2982 S Deacon St | 2025-09-25 |
| 339 Lakewood St | 2025-09-24 |
| 5931 Berkshire St | 2025-09-22 |
| 3028 S Edsel St | 2025-09-16 |
| 11474 Portlance St | 2025-09-11 |
| 5929 Audubon Rd | 2025-09-09 |
| 234 Alter Rd | 2025-09-09 |
| 11917 Lakepointe St | 2025-09-09 |
| 9518 Sanilac St | 2025-09-09 |
| 15366 Patton St | 2025-07-08 |
230 distinct addresses on record; the 14 most recent are shown. Addresses appear as the authority published them. A permit is a filing at an address, not a completed job there.
Permits on record
246 permits; open the 50 most recent
| Permit | Issued | Category | Address in source | Scope as filed | Declared value |
|---|---|---|---|---|---|
| PLM2025-09585 | 2025-10-13 | Plumbing | 364 Lakewood St | Install backwater valve and cleanout. | |
| PLM2025-09586 | 2025-10-13 | Plumbing | 5900 Devonshire Rd | Remove trap and replace with WYE cleanout to camera and clean sewer. | |
| PLM2025-09296 | 2025-09-30 | Plumbing | 8916 Pinehurst St | Install new wall hung lav and diverter. | |
| PLM2025-09295 | 2025-09-30 | Plumbing | 7545 Quinn St | Install new walk in shower, toilet, and pedestal sink. | |
| PLM2025-09185 | 2025-09-25 | Plumbing | 2982 S Deacon St | Installation of exterior backwater valve and cleanout. connect to existing pipe with shielded repair couplings. | |
| PLM2025-09173 | 2025-09-24 | Plumbing | 339 Lakewood St | Install exterior backwater valve and cleanout. Connect to existing sewer with shielded repair couplings. | |
| PLM2025-09152 | 2025-09-22 | Plumbing | 5931 Berkshire St | Install exterior backwater valve and cleanout. | |
| PLM2025-09098 | 2025-09-16 | Plumbing | 3028 S Edsel St | Install backwater valve and WYE cleanout at exterior of home. Connect to existing pipe with shielded repair couplings. | |
| PLM2025-08997 | 2025-09-11 | Plumbing | 11474 Portlance St | Install new water heater and repipe. | |
| PLM2025-08955 | 2025-09-09 | Plumbing | 5929 Audubon Rd | Install new backwater valve and cleanout. Connect to existing sewer lateral with shielded repair couplings. | |
| PLM2025-08954 | 2025-09-09 | Plumbing | 234 Alter Rd | Install new backwater valve and cleanout. Connect to existing sewer lateral with shielded repair couplings. | |
| PLM2025-08952 | 2025-09-09 | Plumbing | 11917 Lakepointe St | Install new backwater valve and cleanout. Connect to existing sewer lateral with shielded repair couplings. | |
| PLM2025-08953 | 2025-09-09 | Plumbing | 9518 Sanilac St | Install new backwater valve and cleanout. Connect to existing sewer lateral with shielded repair couplings. | |
| PLM2025-07707 | 2025-07-08 | Plumbing | 15366 Patton St | Repair exterior sewer in rear yard. Connect to existing sewer with shielded repair couplings. Install WYE cleanout. | |
| PLM2025-07548 | 2025-07-03 | Plumbing | 7842 Longacre St | Install 40 Gal water heater | |
| PLM2025-05039 | 2025-04-22 | Plumbing | 17917 Charest St | Walk in shower with diverter, showerhead, and drain. | |
| PLM2025-04741 | 2025-04-11 | Plumbing | 16591 Greenview Ave | Install new water tank | |
| PLM2025-01719 | 2025-02-07 | Plumbing | 18625 Wisconsin St | Remove interior trap and install WYE cleanout on sanitary line. Install 2 backwater valves. Connect to existing pipes with shielded repair couplings. | |
| PLM2025-01288 | 2025-01-30 | Plumbing | 17311 Santa Barbara Dr | Remove interior trap and install wye cleanout. Install backwater valves on storm and sanitary lines. Connect to existing pipes with shielded repair couplings. | |
| PLM2025-01110 | 2025-01-27 | Plumbing | 15115 Sussex St | Install new floor drain and hot water tank. | |
| PLM2025-01111 | 2025-01-27 | Plumbing | 5039 Grayton St | Remove trap and install WYE cleanout. Install 2 backwater valves. | |
| PLM2025-00156 | 2025-01-08 | Plumbing | 7655 Greenview Ave | Install WYE cleanout and backwater valve. Connect to existing sewer line with shielded repair couplings. | |
| PLM2024-11864 | 2024-12-06 | Plumbing | 18100 Fenmore St | Repair broken sewer. Install WYE cleanout and backwater valve. Install backwater valve. | |
| PLM2024-11845 | 2024-12-06 | Plumbing | 5208 24th St | Install WYE cleanout and backwater valve. Connect to existing sewer line with shielded repair couplings. | |
| PLM2024-11781 | 2024-12-02 | Plumbing | 231 Lakewood St | Install new interior drain tile, sump basket, and pump. Install new backwater valve and WYE cleanout on sanitary line. | |
| PLM2024-11780 | 2024-12-02 | Plumbing | 14919 Rochelle St | Install 2 floor drains and 1 laundry drain. Install cleanout to sanitary line. | |
| PLM2024-11576 | 2024-11-21 | Plumbing | 4810 Lakepointe St | Repair sewer line. connect to existing pipe with shielded repair couplings. Install 2 floor drains. Install WYE cleanout and backwater valve. | |
| PLM2024-11410 | 2024-11-15 | Plumbing | 7429 Braile St | Install backwater valve. Install WYE cleanout. Connect to existing pipe with shielded repair couplings | |
| PLM2024-11411 | 2024-11-15 | Plumbing | 6726 Minock St | Install backwater valve. Install WYE cleanout. Connect to existing pipe with shielded repair couplings | |
| PLM2024-11236 | 2024-11-08 | Plumbing | 4206 Somerset Ave | Install new backwater valve and WYE cleanout. Connect to existing sewer line with shielded repair couplings. | |
| PLM2024-11158 | 2024-11-05 | Plumbing | 5390 Saint Clair St | Install cleanout and backwater valve on sewer line. Connect to existing sewer pipe with shielded repair couplings. | |
| PLM2024-11085 | 2024-10-31 | Plumbing | 4457 Maryland St | Remove trap, install WYE cleanout and 4 backwater valves and 2 floor drains. Connect to existing pipe with shielded repair couplings. | |
| PLM2024-11041 | 2024-10-28 | Plumbing | 10047 Lauder St | Install backwater valve and WYE cleanout. Connect to existing sewer line with shielded repair couplings. | |
| PLM2024-11015 | 2024-10-24 | Plumbing | 4098 Fullerton St | Removal of trap and installation of WYE cleanout and backwater valves. | |
| PLM2024-09475 | 2024-10-22 | Plumbing | 2921 Baldwin St | Install 2 interior backwater valves. Install WYE cleanout on sanitary and trap on storm. | |
| PLM2024-10932 | 2024-10-21 | Plumbing | 9412 Manor | Install backwater valve and WYE cleanout. Connect to existing sewer with shielded repair couplings. | |
| PLM2024-10785 | 2024-10-14 | Plumbing | 18294 Ferguson St | Remove sanitary trap in basement and install WYE cleanout. Install 2 backwater valves. One on sanitary and one on storm line. | |
| PLM2024-10784 | 2024-10-14 | Plumbing | 14919 Rochelle St | Repair broken section of pipe and replace. Install shielded repair couplings to connect new pipe to existing. | |
| PLM2024-10579 | 2024-10-08 | Plumbing | 15339 Patton St | Remove existing trap on sanitary line. Install WYE cleanout and backwater valve. Run existing storm line to the newly installed sump basket done by another contractor on separate p | |
| PLM2024-10240 | 2024-10-03 | Plumbing | 21145 Santa Clara Ave | Repair interior drain lines. Install 2 floor drains. Install backwater valve and WYE cleanout. | |
| PLM2024-10065 | 2024-10-01 | Plumbing | 7247 Wykes St | Install backwater valve. Connect to existing pipe with shielded repair couplings. | |
| PLM2024-10066 | 2024-10-01 | Plumbing | 5220 Chatsworth St | Install backwater valve. connect to existing sewer with shielded repair couplings. | |
| PLM2024-10031 | 2024-09-30 | Plumbing | 5607 Lonyo St | Install backwater valve. Connect to existing pipe with shielded repair couplings. Install WYE cleanout. | |
| PLM2024-10030 | 2024-09-30 | Plumbing | 7762 Vaughan St | Install backwater valve. Connect to existing pipe with shielded repair couplings. Install WYE cleanout. | |
| PLM2024-09830 | 2024-09-24 | Plumbing | 13224 Tireman Ave | Install exterior backwater valve and wye cleanout. Connect to existing sewer lateral with shielded repair couplings. | |
| PLM2024-09663 | 2024-09-17 | Plumbing | 6638 Floyd St | Install exterior backwater valve and WYE cleanout. Connect to existing sewer line with shielded repair couplings. | |
| PLM2024-09304 | 2024-09-10 | Plumbing | 17216 Chapel St | Install sump basket and pump for new interior drain tile around perimeter of the basement. | |
| PLM2024-09303 | 2024-09-10 | Plumbing | 767 Kitchener St | Install 2 new backwater valves on the interior. Connect to existing pipes with shielded repair couplings. | |
| PLM2024-09302 | 2024-09-10 | Plumbing | 9264 Littlefield St | Install 2 new backwater valves on the interior. Connect to existing pipes with shielded repair couplings. | |
| PLM2024-09097 | 2024-09-09 | Plumbing | 9271 Littlefield St | Install exterior backwater valve. Connect to existing pipe with shielded repair couplings. |
Fields appear as the issuing authority published them, including spelling and blanks. Scope text is the applicant's description of intended work, not an inspection finding.
Source and limits
Public Detroit permit records through 2025, counted by distinct permit number. This is a historical filing record: it cannot show current backlog, pricing, crew availability, licensing or insurance, and a quiet period may only mean work was filed elsewhere. Confirm anything commercial with the company and with the issuing authority before acting. How we build these records, and what we withhold →